Loxahatchee, Palm Beach County, Florida · FPL · operated by Florida Power & Light Co · owned by Nextera Energy Inc
The largest power plant in Florida by capacity — 4,263 MW, 100% natural gas by fuel energy in 2023, first unit online in 2009.
| Unit | Capacity MW | Fuel | Technology | Online | Status |
|---|---|---|---|---|---|
| Unit 1ST | 527.0 | Natural Gas | Natural Gas Fired Combined Cycle | 2009 | Operating |
| Unit 2ST | 527.0 | Natural Gas | Natural Gas Fired Combined Cycle | 2009 | Operating |
| Unit 3ST | 527.0 | Natural Gas | Natural Gas Fired Combined Cycle | 2011 | Operating |
| Unit 1A | 298.0 | Natural Gas | Natural Gas Fired Combined Cycle | 2009 | Operating |
| Unit 1B | 298.0 | Natural Gas | Natural Gas Fired Combined Cycle | 2009 | Operating |
| Unit 1C | 298.0 | Natural Gas | Natural Gas Fired Combined Cycle | 2009 | Operating |
| Unit 2A | 298.0 | Natural Gas | Natural Gas Fired Combined Cycle | 2009 | Operating |
| Unit 2B | 298.0 | Natural Gas | Natural Gas Fired Combined Cycle | 2009 | Operating |
| Unit 2C | 298.0 | Natural Gas | Natural Gas Fired Combined Cycle | 2009 | Operating |
| Unit 3A | 298.0 | Natural Gas | Natural Gas Fired Combined Cycle | 2011 | Operating |
| Unit 3B | 298.0 | Natural Gas | Natural Gas Fired Combined Cycle | 2011 | Operating |
| Unit 3C | 298.0 | Natural Gas | Natural Gas Fired Combined Cycle | 2011 | Operating |
All 12 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; co-firing fuels and fuel-switching times; NOₓ, particulate and mercury controls with compliance years; cooling system and water source with withdrawal rate; stack height.
See the engineering record →| Supplier | Fuel | Delivered TBtu | Tons | Mine of origin | Transport |
|---|---|---|---|---|---|
| Florida Gas Transmission | Natural gas | 140 | n/a | n/a | Pipeline |
Figures are volumes delivered in 2023, not volumes burned. Tons are shown for coal only.