Fuel spend$2.55M2023 · estimate
Capacity in service45.0MW1 unit · waste
Net generation298GWh2023 · reported
CO₂ emitted238,157t2023 · reported to EPA · 1,406th highest of 6,030 in the US
Rank in New Jersey#27of 407 · by capacity · #3,649 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor76%2023
1 unit shown. Behind it, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; SO₂ scrubber type, sorbent and removal efficiency; NOₓ, particulate and mercury controls with compliance years; ownership stakes where a unit is jointly held.
See the engineering record →
How big is Union County Resource Recovery Facility?
45.0 MW across 1 generating unit in service.
Who owns and operates it?
Owned by
Covanta Holding Corp (100%) and operated by Reworld Union (NJ), LLC, filed as independent power producer.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's ReliabilityFirst region.
How old is it?
The capacity-weighted average megawatt here came online in 1994.
When is it due to retire?
No retirement date has been filed for any operating unit at Union County Resource Recovery Facility. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned other fuels.
How much does it spend on fuel?
An estimated $2.55M in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
How much CO₂ does it emit?
238,157 t in 2023, reported to the EPA — the 1,406th highest of 6,030 US facilities that reported. Up from 201,040 t in 2011.