AMERICAN ENERGY ATLAS
Power·California

Campbell Power Plant

Sacramento, Sacramento County, California · BANC · operated by Sacramento Municipal Util Dist · owned by Sacramento Municipal Utility District Financing Authority

2023 · headline year
Fuel spend$41.2M2023 · estimate
Capacity in service174MW2 units · gas
Net generation616GWh2023 · reported
CO₂ emitted275,040t2023 · reported to EPA · 1,296th highest of 6,030 in the US
Rank in California#137of 1,713 · by capacity · #1,662 of 13,147 US
Reported suppliersNot reported2023 · last deliveries 2011
Capacity factor40%2023

Location

Sacramento County · BANC · WECC

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 4.95 TBtu · reported · $41.2M est.

CO₂ emitted, t · 2011–2023

0200,000400,000600,000201120172023
Reported (through 2023)

Generating units

2 of 2 shown · 174 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit CCCT118.7Natural GasNatural Gas Fired Combined Cycle1997Operating
Unit CCST55.2Natural GasNatural Gas Fired Combined Cycle1997Operating

All 2 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; NOₓ, particulate and mercury controls with compliance years; ownership stakes where a unit is jointly held.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023. 1,176 deliveries are on record for 2011.

Delivery history. Subscribe to see every recorded delivery, supplier, mine of origin and transport mode.

See the delivery history →

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Sacramento Municipal Util Dist
Entity type
Political Subdivision
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1001130
Balancing authority
BANC
NERC region
WECC
Gas pipeline
Pacific Gas
EIA plant ID
7552

Common questions

How big is Campbell Power Plant?
174 MW across 2 generating units in service.
Who owns and operates it?
Owned by Sacramento Municipal Utility District Financing Authority (100%) and operated by Sacramento Municipal Util Dist, filed as political subdivision.
Which grid does it sell into?
BANC (Balancing Authority of Northern California) is its balancing authority, inside NERC's WECC region.
How old is it?
The capacity-weighted average megawatt here came online in 1997. Every operating unit came online in 1997.
When is it due to retire?
No retirement date has been filed for any operating unit at Campbell Power Plant. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas.
How much does it spend on fuel?
An estimated $41.2M in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
How much CO₂ does it emit?
275,040 t in 2023, reported to the EPA — the 1,296th highest of 6,030 US facilities that reported. Up from 204,715 t in 2011.

Related pages

California energyAll facilities in the state→Centinela Solar Energy175 MW operating capacity→ Big Creek 3174 MW operating capacity→ Richmond Cogen174 MW operating capacity→ Blythe Solar 110, LLC173 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming