AMERICAN ENERGY ATLAS
Power·Wisconsin

Weston

Kronenwetter, Marathon County, Wisconsin · MISO · operated by Wisconsin Public Service Corp · owned by Wec Energy Group Inc and Dairyland Power Cooperative

2023 · headline year
Fuel spend$81.7M2023 · estimate
Capacity in service946MW2 units · coal
Net generation3.43TWh2023 · reported
CO₂ emitted3.03Mt2023 · reported to EPA · 158th highest of 6,030 in the US
Rank in Wisconsin#6of 258 · by capacity · #328 of 13,147 US
Reported suppliers42023 · 56 deliveries
Capacity factor41%2023

Location

Marathon County · MISO · RFC

What it burns

2023 · reported

Share of reported fuel consumption

99% Coal · 32.9 TBtu · reported · $81.1M est.1% Natural gas · 0.166 TBtu · reported · $566,713 est.

Coal supplies 99% of the fuel energy it burned in 2023.

CO₂ emitted, Mt · 2011–2023

0246201120172023
Reported (through 2023)

Generating units

6 of 6 shown · 946 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 4595.0SubbituminousConventional Steam Coal2008Operating
Unit 3350.5SubbituminousConventional Steam Coal1981Operating
Unit 281.6Natural GasNatural Gas Steam Turbine1960Retired 2023
Unit 160.0SubbituminousConventional Steam Coal1954Retired 2015
Unit 3256.7Natural GasNatural Gas Fired Combustion Turbine1973Retired 2023
Unit 3119.6Natural GasNatural Gas Fired Combustion Turbine1969Retired 2023

All 6 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; co-firing fuels and fuel-switching times; SO₂ scrubber type, sorbent and removal efficiency; NOₓ, particulate and mercury controls with compliance years; cooling system and water source with withdrawal rate; stack height; ownership stakes where a unit is jointly held.

See the engineering record →

Who supplies the fuel

1 of 4 suppliers · delivered in 2023
SupplierFuelDelivered TBtuTonsMine of originTransport
Peabody Coal SalesCoal191,071,835North Antelope Rochelle Mine, WyomingRail

Figures are volumes delivered in 2023, not volumes burned. Tons are shown for coal only.

Showing 1 of 4 suppliers. Subscribe to see all 4, every one of the 823 deliveries recorded 2011–2023, mine-level origins, transport mode and the delivered price paid — plus sorting, filtering and Excel export.

See all 4 suppliers →

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Wisconsin Public Service Corp
Jointly held units
Dairyland Power Coop 30% of 1 unit
Wisconsin Public Service Corp 70% of 1 unit
Entity type
Investor-Owned Utility
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1000986
Balancing authority
MISO
NERC region
ReliabilityFirst (RFC)
EIA plant ID
4078

Common questions

How big is Weston?
946 MW across 2 generating units in service. A further 4 units are listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Owned by Wec Energy Group Inc and Dairyland Power Cooperative and operated by Wisconsin Public Service Corp, filed as investor-owned utility. 2 owner stakes are filed on jointly held units.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's ReliabilityFirst region.
How old is it?
The capacity-weighted average megawatt here came online in 1998. The oldest operating unit is Unit 3 (1981); the newest is Unit 4 (2008).
When is it due to retire?
No retirement date has been filed for any operating unit at Weston. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned coal and natural gas. Coal delivered in 2023 came from 3 coal suppliers, from mines in Wyoming — principally North Antelope Rochelle Mine. Other fuels (natural gas) came from 1 supplier in 2023.
How much does it spend on fuel?
An estimated $81.7M in 2023 — coal $81.1M and natural gas $566,713. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
How much CO₂ does it emit?
3.03 Mt in 2023, reported to the EPA — the 158th highest of 6,030 US facilities that reported. Down from 5.59 Mt in 2011.

Also at this site

Weston RICESame site · operating→

Related pages

Wisconsin energyAll facilities in the state→Port Washington Generating Station1,230 MW operating capacity→ Columbia1,112 MW operating capacity→ South Oak Creek642 MW operating capacity→ Fox Energy Center619 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming