54.0 MW across 1 generating unit in service. A further 3 units are listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Operated by UNS Electric, Inc, filed as investor-owned utility.
Which grid does it sell into?
TEPC (Tucson Electric Power Company) is its balancing authority, inside NERC's WECC region.
How old is it?
The capacity-weighted average megawatt here came online in 2006.
When is it due to retire?
No retirement date has been filed for any operating unit at Valencia. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas and oil & petroleum.
How much does it spend on fuel?
An estimated $436,253 in 2023 — natural gas $321,034 and oil & petroleum $115,219. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.