Bedford, Trimble County, Kentucky · LGEE · operated by Louisville Gas & Electric Co · owned by PPL Corp

2023 · headline year

The largest power plant in Kentucky by capacity — 2,594 MW, 94% coal by fuel energy in 2023, first unit online in 1990, newest in 2011.

Reported fuel cost$195M2023 · reported deliveries
Capacity in service2,594MW8 units · coal + gas
Net generation7.37TWh2023 · reported
CO₂ emitted6.99Mt2023 · reported to EPA · 35th highest of 6,030 in the US
Rank in Kentucky#1of 58 · by capacity · #27 of 13,147 US
Reported suppliers102023 · 126 deliveries
Capacity factor32%2023

Location

Trimble County · LGEE · SERC

What it burns

2023 · reported

Share of reported fuel consumption

94% Coal · 68.7 TBtu · reported6% Natural gas · 4.51 TBtu · reported

Coal supplies 94% of the fuel energy it burned in 2023.

CO₂ emitted, Mt · 2011–2023

0369201120172023
Reported (through 2023)

Generating units

8 of 8 shown · 2,594 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 2834.0Bituminous coalConventional Steam Coal2011Operating
Unit 1566.1Bituminous coalConventional Steam Coal1990Operating
Unit 10199.0Natural GasNatural Gas Fired Combustion Turbine2004Operating
Unit 5199.0Natural GasNatural Gas Fired Combustion Turbine2002Operating
Unit 6199.0Natural GasNatural Gas Fired Combustion Turbine2002Operating
Unit 7199.0Natural GasNatural Gas Fired Combustion Turbine2004Operating
Unit 8199.0Natural GasNatural Gas Fired Combustion Turbine2004Operating
Unit 9199.0Natural GasNatural Gas Fired Combustion Turbine2004Operating

All 8 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; co-firing fuels and fuel-switching times; SO₂ scrubber type, sorbent and removal efficiency; NOₓ, particulate and mercury controls with compliance years; cooling system and water source with withdrawal rate; stack height; ownership stakes where a unit is jointly held.

See the engineering record →

Who supplies the fuel

1 of 10 suppliers · delivered in 2023
SupplierFuelDelivered TBtuTonsMine of originTransport
Alliance CoalCoal42.71,856,107River View Mine, Kentucky + 2 moreRiver barge

Figures are volumes delivered in 2023, not volumes burned. Tons are shown for coal only.

Showing 1 of 10 suppliers. Subscribe to see all 10, every one of the 1,767 deliveries recorded 2011–2023, mine-level origins, transport mode and the delivered price paid — plus sorting, filtering and Excel export.

See all 10 suppliers →

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
PPL Corp
Operating utility
Louisville Gas & Electric Co
Jointly held units
Illinois Municipal Elec Agency 12% of 2 units
Indiana Municipal Power Agency 13% of 2 units
Kentucky Utilities Co partial of 7 units
Louisville Gas & Electric Co partial of 8 units
Entity type
Investor-Owned Utility
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1006542
Balancing authority
LGEE
NERC region
SERC
Gas pipeline
West Texas Gas Inc
EIA plant ID
6071

Common questions

How big is Trimble County?
2,594 MW across 8 generating units in service — 1,400 MW of coal and 1,194 MW of natural gas.
Who owns and operates it?
Owned by PPL Corp and operated by Louisville Gas & Electric Co, filed as investor-owned utility. 4 owner stakes are filed on jointly held units.
Which grid does it sell into?
LGEE (Louisville Gas and Electric Company and Kentucky Utilities Company) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 2003. The oldest operating unit is Unit 1 (1990); the newest is Unit 2 (2011).
When is it due to retire?
No retirement date has been filed for any operating unit at Trimble County. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned coal and natural gas. Coal delivered in 2023 came from 9 coal suppliers, from mines in Illinois, West Virginia and Kentucky — principally River View Mine. Other fuels (natural gas) came from 1 supplier in 2023.
How much does it spend on fuel?
Its fuel receipts report a delivered cost of $195M in 2023.
How much CO₂ does it emit?
6.99 Mt in 2023, reported to the EPA — the 35th highest of 6,030 US facilities that reported. Down from 7.56 Mt in 2011.

Related pages

Kentucky energyAll facilities in the state→Ghent2,226 MW operating capacity→ Paradise1,854 MW operating capacity→ H L Spurlock1,608 MW operating capacity→ Shawnee1,575 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming