AMERICAN ENERGY ATLAS
Power·Florida

Treasure Coast Energy Center

Fort Pierce, ST. Lucie County, Florida · FMPP · operated by Fort Pierce Utilities Authority · owned by Florida Municipal Power Agency

2023 · headline year
Reported fuel cost$44.5M2023 · reported deliveries
Capacity in service411MW2 units · gas
Net generation1.79TWh2023 · reported
CO₂ emitted716,181t2023 · reported to EPA · 771st highest of 6,030 in the US
Rank in Florida#40of 310 · by capacity · #807 of 13,147 US
Reported suppliers22023 · 15 deliveries
Capacity factor50%2023

Location

ST. Lucie County · FMPP · SERC

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 12.8 TBtu · reported

CO₂ emitted, t · 2011–2023

0300,000600,000900,000201120172023
Reported (through 2023)

Generating units

2 of 2 shown · 411 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit CT1219.6Natural GasNatural Gas Fired Combined Cycle2008Operating
Unit ST1191.8Natural GasNatural Gas Fired Combined Cycle2008Operating

All 2 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; co-firing fuels and fuel-switching times; NOₓ, particulate and mercury controls with compliance years; cooling system and water source with withdrawal rate; stack height; ownership stakes where a unit is jointly held.

See the engineering record →

Who supplies the fuel

1 of 2 suppliers · delivered in 2023
SupplierFuelDelivered TBtuTonsMine of originTransport
Florida GasNatural gas12.8n/an/aPipeline

Figures are volumes delivered in 2023, not volumes burned. Tons are shown for coal only. Deliveries and consumption are reported separately and need not match in a year (stockpiles, and pipeline gas that fuel receipts do not capture).

Showing 1 of 2 suppliers. Subscribe to see all 2, every one of the 159 deliveries recorded 2011–2023, mine-level origins, transport mode and the delivered price paid — plus sorting, filtering and Excel export.

See all 2 suppliers →

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
Florida Municipal Power Agency · 100%
Operating utility
Fort Pierce Utilities Authority
Entity type
Municipally Owned Utility
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1002818
Balancing authority
FMPP
NERC region
SERC
EIA plant ID
56400

Common questions

How big is Treasure Coast Energy Center?
411 MW across 2 generating units in service.
Who owns and operates it?
Owned by Florida Municipal Power Agency (100%) and operated by Fort Pierce Utilities Authority, filed as municipally owned utility.
Which grid does it sell into?
FMPP (Florida Municipal Power Pool) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 2008. Every operating unit came online in 2008.
When is it due to retire?
No retirement date has been filed for any operating unit at Treasure Coast Energy Center. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas. Natural gas and oil & petroleum came from 2 suppliers in 2023.
How much does it spend on fuel?
Its fuel receipts report a delivered cost of $44.5M in 2023.
How much CO₂ does it emit?
716,181 t in 2023, reported to the EPA — the 771st highest of 6,030 US facilities that reported. Up from 646,724 t in 2011.

Related pages

Florida energyAll facilities in the state→Manatee Solar Energy Center484 MW operating capacity→ Hardee Power Station470 MW operating capacity→ Greenland Energy Center381 MW operating capacity→ J D Kennedy370 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming