Figures are volumes delivered in 2023, not volumes burned. Tons are shown for coal only.
The supplier is shown. Subscribe to see every one of the 156 deliveries recorded 2011–2023, mine-level origins, transport mode and the delivered price paid — plus sorting, filtering and Excel export.
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's MRO region.
How old is it?
The capacity-weighted average megawatt here came online in 2001. Every operating unit came online in 2001.
When is it due to retire?
No retirement date has been filed for any operating unit at Rockgen Energy Center. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas. Natural gas came from 1 supplier in 2023.
How much does it spend on fuel?
Its fuel receipts report a delivered cost of $15.6M in 2023.
How much CO₂ does it emit?
349,879 t in 2023, reported to the EPA — the 1,141st highest of 6,030 US facilities that reported. Up from 110,365 t in 2011.