CO₂ emitted2.09Mt2023 · reported to EPA · 288th highest of 6,030 in the US
Rank in Wisconsin#10of 258 · by capacity · #806 of 13,147 US
Reported suppliers42023 · 23 deliveries
Capacity factor53%2023
Location
What it burns
2023 · reported
Share of reported fuel consumption
100% Coal · 21.3 TBtu · reported
CO₂ emitted, Mt · 2011–2023
Reported (through 2023)
Generating units
4 of 4 shown · 414 MW in service
Unit
Capacity MW
Fuel
Technology
Online
Status
Unit 5
413.7
Subbituminous
Conventional Steam Coal
1985
Operating
Unit BESS1
99.0
Storage
Batteries
2026
Proposed
Unit 4
351.0
Subbituminous
Conventional Steam Coal
1969
Retired 2018
Unit 3
69.0
Subbituminous
Conventional Steam Coal
1951
Retired 2015
All 4 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; SO₂ scrubber type, sorbent and removal efficiency; NOₓ, particulate and mercury controls with compliance years; cooling system and water source with withdrawal rate; stack height; ownership stakes where a unit is jointly held.
Figures are volumes delivered in 2023, not volumes burned. Tons are shown for coal only.
Showing 1 of 4 suppliers. Subscribe to see all 4, every one of the 793 deliveries recorded 2011–2023, mine-level origins, transport mode and the delivered price paid — plus sorting, filtering and Excel export.
Wisconsin Power & Light Co 68% of 1 unit Wisconsin Public Service Corp 32% of 1 unit
Entity type
Investor-Owned Utility
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1000983
Balancing authority
MISO
NERC region
MRO
EIA plant ID
4050
Common questions
How big is Edgewater (4050)?
414 MW across 1 generating unit in service. A further 3 units are listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Owned by Alliant Energy Corp (100%) and operated by Wisconsin Power & Light Co, filed as investor-owned utility. 2 owner stakes are filed on jointly held units.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's MRO region.
How old is it?
The capacity-weighted average megawatt here came online in 1985.
When is it due to retire?
No retirement date has been filed for any operating unit at Edgewater (4050). An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned coal. Coal delivered in 2023 came from 3 coal suppliers, from mines in Wyoming — principally North Antelope Rochelle Mine. Other fuels (oil & petroleum) came from 1 supplier in 2023.
How much does it spend on fuel?
Its fuel receipts report a delivered cost of $46.2M in 2023.
How much CO₂ does it emit?
2.09 Mt in 2023, reported to the EPA — the 288th highest of 6,030 US facilities that reported. Down from 4.41 Mt in 2011.