AMERICAN ENERGY ATLAS
Power·Utah

Provo Power Plant

Utah County, Utah · PACE · operated by Utah Municipal Power Agency

2023 · headline year
Fuel spend$570,2022023 · estimate
Capacity in service12.0MW5 units · gas
Net generation7.12GWh2023 · reported
Rank in Utah#60of 123 · by capacity · #5,143 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor7%2023

Location

Utah County · PACE · WECC

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 71,428 MMBtu · reported · $570,202 est.

Reported fuel consumption, MMBtu · 2017–23

030,00060,00090,000201720202023
Reported (through 2023)

Generating units

5 of 5 shown · 12.0 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 12.4Natural GasNatural Gas Internal Combustion Engine2018Operating
Unit 22.4Natural GasNatural Gas Internal Combustion Engine2018Operating
Unit 32.4Natural GasNatural Gas Internal Combustion Engine2018Operating
Unit 42.4Natural GasNatural Gas Internal Combustion Engine2018Operating
Unit 52.4Natural GasNatural Gas Internal Combustion Engine2018Operating

All 5 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Utah Municipal Power Agency
Entity type
Political Subdivision
Regulatory status
Regulated
Balancing authority
PACE
NERC region
WECC
EIA plant ID
61508

Common questions

How big is Provo Power Plant?
12.0 MW across 5 generating units in service.
Who owns and operates it?
Operated by Utah Municipal Power Agency, filed as political subdivision.
Which grid does it sell into?
PACE (PacifiCorp - East) is its balancing authority, inside NERC's WECC region.
How old is it?
The capacity-weighted average megawatt here came online in 2018. Every operating unit came online in 2018.
When is it due to retire?
No retirement date has been filed for any operating unit at Provo Power Plant. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas.
How much does it spend on fuel?
An estimated $570,202 in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.

Related pages

Utah energyAll facilities in the state→Thermo No 114.0 MW operating capacity→ Jordanelle Dam Hydroelectric Project13.0 MW operating capacity→ Bloomington Power Plant10.2 MW operating capacity→ Hurricane City Power10.0 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming