AMERICAN ENERGY ATLAS
Power·Florida

Pasco Cnty Solid Waste Resource Recovery

Pasco County, Florida · FPC · operated by Pasco County

2023 · headline year
Capacity in service31.2MW1 unit · waste
Net generation186GWh2023 · reported
Rank in Florida#232of 310 · by capacity · #3,985 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor68%2023

Location

Pasco County · FPC · SERC

What it burns

2023 · reported

Share of reported fuel consumption

100% Other fuels · 3.52 TBtu · reported

Reported fuel consumption, TBtu · 2011–2023

0246201120172023
Reported (through 2023)

Generating units

2 of 2 shown · 31.2 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit GEN131.2Municipal solid wasteMunicipal Solid Waste1991Operating
Unit GEN220.0Municipal solid wasteMunicipal Solid Waste2026Proposed

All 2 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; SO₂ scrubber type, sorbent and removal efficiency; NOₓ, particulate and mercury controls with compliance years.

See the engineering record →
UnitEventWhenMW
Unit GEN2new unit202620.0 MW

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Pasco County
Entity type
Municipally Owned Utility
Regulatory status
Not Regulated
Balancing authority
FPC
NERC region
SERC
EIA plant ID
50666

Common questions

How big is Pasco Cnty Solid Waste Resource Recovery?
31.2 MW across 1 generating unit in service. A further 1 unit is listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Operated by Pasco County, filed as municipally owned utility.
Which grid does it sell into?
FPC (Progress Energy Florida) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 1991.
When is it due to retire?
No retirement date has been filed for any operating unit at Pasco Cnty Solid Waste Resource Recovery. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned other fuels.

Also at this site

PCSW Resource Recovery FacilitySame site→

Related pages

Florida energyAll facilities in the state→G W Ivey35.6 MW operating capacity→ Big Bend 1 Solar and Battery Storage32.4 MW operating capacity→ WestRock CP, LLC - Seminole Mill (Formerly Smurfit-Stone)30.0 MW operating capacity→ Gulf Coast Solar Center I30.0 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming