Marion Heights, Northumberland County, Pennsylvania · PJM · operated by Mount Carmel Cogen Inc · owned by MT Carmel Cogen Inc

2023 · headline year
Fuel spend$15.6M2023 · estimate
Capacity in service47.3MW1 unit · coal
Net generation104GWh2023 · reported
CO₂ emitted250,388t2023 · reported to EPA · 1,368th highest of 6,030 in the US
Rank in Pennsylvania#96of 256 · by capacity · #3,599 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor25%2023

Location

Northumberland County · PJM · RFC

What it burns

2023 · reported

Share of reported fuel consumption

94% Coal · 1.95 TBtu · reported · $15.6M est.6% Natural gas · 0.135 TBtu · reported · $1,929 est.

Coal supplies 94% of the fuel energy it burned in 2023.

CO₂ emitted, t · 2011–2023

0200,000400,000600,000201120172023
Reported (through 2023)

Generating units

1 of 1 shown · 47.3 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit TG147.3Waste coalConventional Steam Coal1990Operating

1 unit shown. Behind it, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; co-firing fuels and fuel-switching times; SO₂ scrubber type, sorbent and removal efficiency; NOₓ, particulate and mercury controls with compliance years.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
MT Carmel Cogen Inc · 100%
Operating utility
Mount Carmel Cogen Inc
Entity type
Independent Power Producer
Regulatory status
Not Regulated
Industry sector
Power Plants
EPA facility ID
1001210
Balancing authority
PJM
NERC region
ReliabilityFirst (RFC)
EIA plant ID
10343

Common questions

How big is Mt. Carmel Cogeneration?
47.3 MW across 1 generating unit in service.
Who owns and operates it?
Owned by MT Carmel Cogen Inc (100%) and operated by Mount Carmel Cogen Inc, filed as independent power producer.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's ReliabilityFirst region.
How old is it?
The capacity-weighted average megawatt here came online in 1990.
When is it due to retire?
No retirement date has been filed for any operating unit at Mt. Carmel Cogeneration. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned coal and natural gas.
How much does it spend on fuel?
An estimated $15.6M in 2023 — coal $15.6M and natural gas $1,929. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
How much CO₂ does it emit?
250,388 t in 2023, reported to the EPA — the 1,368th highest of 6,030 US facilities that reported. Down from 444,048 t in 2011.

Related pages

Pennsylvania energyAll facilities in the state→South Chestnut LLC50.4 MW operating capacity→ Sandy Ridge Wind Farm50.0 MW operating capacity→ Hunlock Unit 444.0 MW operating capacity→ Wallenpaupack40.0 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming