AMERICAN ENERGY ATLAS
Power·Arizona

Mesquite Solar 1

Maricopa County, Arizona · CAISO · operated by Consolidated Edison Development Inc.

2023 · headline year
Fuel spend$02023 · no purchased fuel
Capacity in service170MW12 units · solar
Rank in Arizona#41of 166 · by capacity · #1,685 (tied) of 13,147 US

Location

Maricopa County · CAISO · WECC

Generating units

12 of 12 shown · 170 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 116.0SolarSolar Photovoltaic2011Operating
Unit 1116.0SolarSolar Photovoltaic2012Operating
Unit 1216.0SolarSolar Photovoltaic2012Operating
Unit 216.0SolarSolar Photovoltaic2012Operating
Unit 416.0SolarSolar Photovoltaic2012Operating
Unit 516.0SolarSolar Photovoltaic2012Operating
Unit 716.0SolarSolar Photovoltaic2012Operating
Unit 916.0SolarSolar Photovoltaic2012Operating
Unit 1012.0SolarSolar Photovoltaic2012Operating
Unit 812.0SolarSolar Photovoltaic2012Operating
Unit 310.0SolarSolar Photovoltaic2011Operating
Unit 68.0SolarSolar Photovoltaic2012Operating

All 12 units shown. Behind each one, AEA holds the full engineering record: panel technology, tracking and DC capacity.

See the engineering record →

Ownership & operations

Operating utility
Consolidated Edison Development Inc.
Entity type
Independent Power Producer
Regulatory status
Not Regulated
Balancing authority
CAISO
NERC region
WECC
EIA plant ID
57707

Common questions

How big is Mesquite Solar 1?
170 MW across 12 generating units in service.
Who owns and operates it?
Operated by Consolidated Edison Development Inc., filed as independent power producer.
Which grid does it sell into?
CAISO (California Independent System Operator) is its balancing authority, inside NERC's WECC region.
How old is it?
The capacity-weighted average megawatt here came online in 2012. The oldest operating units are Unit 1 and Unit 3 (2011); the newest are Unit 11, Unit 12, Unit 2, Unit 4 and 6 more (2012).
When is it due to retire?
No retirement date has been filed for any operating unit at Mesquite Solar 1. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it run on?
Solar Photovoltaic (170 MW).
How much does it spend on fuel?
Nothing in 2023 — its units in service (solar photovoltaic) burn no fuel, and it reports no fuel consumption to the EIA.

Related pages

Arizona energyAll facilities in the state→APS Saguaro Power Plant184 MW operating capacity→ White Wing Solar179 MW operating capacity→ Babbitt Ranch Energy Center163 MW operating capacity→ Sun Streams, LLC160 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming