Newark, Independence County, Arkansas · MISO · operated by Entergy Arkansas LLC · owned by Entergy Corp, Arkansas Electric Cooperative Corp, City Water & Light Plant of the City of Jonesboro Arkansas and 4 more

2023 · headline year

The joint 3rd-largest power plant in Arkansas by capacity — 1,800 MW, 100% coal by fuel energy in 2023, first unit online in 1983.

Reported fuel cost$126M2023 · reported deliveries
Capacity in service1,800MW2 units · coal
Net generation4.74TWh2023 · reported
CO₂ emitted5.57Mt2023 · reported to EPA · 58th highest of 6,030 in the US
Rank in Arkansas#3 (tied)of 108 · by capacity · #97 (tied) of 13,147 US
Reported suppliers52023 · 65 deliveries
Capacity factor30%2023

Location

Independence County · MISO · SERC

What it burns

2023 · reported

Share of reported fuel consumption

100% Coal · 51 TBtu · reported

CO₂ emitted, Mt · 2011–2023

051015201120172023
Reported (through 2023)

Generating units

2 of 2 shown · 1,800 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 1900.0SubbituminousConventional Steam Coal1983Operating
Unit 2900.0SubbituminousConventional Steam Coal1984Operating

All 2 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; NOₓ, particulate and mercury controls with compliance years; cooling system and water source with withdrawal rate; stack height; ownership stakes where a unit is jointly held.

See the engineering record →

Who supplies the fuel

1 of 5 suppliers · delivered in 2023
SupplierFuelDelivered TBtuTonsMine of originTransport
Arch Coal SalesCoal24.41,355,152Black Thunder, WyomingRail

Figures are volumes delivered in 2023, not volumes burned. Tons are shown for coal only.

Showing 1 of 5 suppliers. Subscribe to see all 5, every one of the 916 deliveries recorded 2011–2023, mine-level origins, transport mode and the delivered price paid — plus sorting, filtering and Excel export.

See all 5 suppliers →

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Entergy Arkansas LLC
Jointly held units
Arkansas Electric Coop Corp 35% of 2 units
City Water and Light Plant partial of 2 units
City of Osceola - (AR) <1% of 2 units
City of West Memphis - (AR) 1% of 2 units
Conway Corporation 2% of 2 units
East Texas Electric Coop, Inc 7% of 1 unit
+ 3 more
Entity type
Investor-Owned Utility
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1001059
Balancing authority
MISO
NERC region
SERC
EIA plant ID
6641

Common questions

How big is Independence?
1,800 MW across 2 generating units in service.
Who owns and operates it?
Owned by Entergy Corp, Arkansas Electric Cooperative Corp, City Water & Light Plant of the City of Jonesboro Arkansas and 4 more and operated by Entergy Arkansas LLC, filed as investor-owned utility. 9 owner stakes are filed on jointly held units.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 1984. The oldest operating unit is Unit 1 (1983); the newest is Unit 2 (1984).
When is it due to retire?
No retirement date has been filed for any operating unit at Independence. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned coal. Coal delivered in 2023 came from 3 coal suppliers, from mines in Wyoming — principally Black Thunder. Other fuels (oil & petroleum) came from 2 suppliers in 2023.
How much does it spend on fuel?
Its fuel receipts report a delivered cost of $126M in 2023.
How much CO₂ does it emit?
5.57 Mt in 2023, reported to the EPA — the 58th highest of 6,030 US facilities that reported. Down from 10.9 Mt in 2011.

Related pages

Arkansas energyAll facilities in the state→Union Power Station2,428 MW operating capacity→ Arkansas Nuclear One1,845 MW operating capacity→ White Bluff1,800 MW operating capacity→ Magnet Cove Generating Station746 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming