AMERICAN ENERGY ATLAS
Power·Missouri

Holden Power Plant

Holden, Johnson County, Missouri · AECI · operated by Associated Electric Coop, Inc · owned by Associated Electric Cooperative Inc

2023 · headline year
Reported fuel cost$6M2023 · reported deliveries
Capacity in service321MW3 units · gas
Net generation197GWh2023 · reported
CO₂ emitted135,920t2023 · reported to EPA · 1,963rd highest of 6,030 in the US
Rank in Missouri#18of 119 · by capacity · #942 of 13,147 US
Reported suppliers82023 · 96 deliveries
Capacity factor7%2023

Location

Johnson County · AECI · SERC

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 2.96 TBtu · reported

CO₂ emitted, t · 2011–2023

050,000100,000150,000201120172023
Reported (through 2023)

Generating units

3 of 3 shown · 321 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 11107.1Natural GasNatural Gas Fired Combustion Turbine2002Operating
Unit 12107.1Natural GasNatural Gas Fired Combustion Turbine2002Operating
Unit 13107.1Natural GasNatural Gas Fired Combustion Turbine2002Operating

All 3 units shown. Behind each one, AEA holds the full engineering record: co-firing fuels and fuel-switching times.

See the engineering record →

Who supplies the fuel

1 of 8 suppliers · delivered in 2023
SupplierFuelDelivered TBtuTonsMine of originTransport
Clearwater EnterprisesNatural gas1.07n/an/aPipeline

Figures are volumes delivered in 2023, not volumes burned. Tons are shown for coal only. Deliveries and consumption are reported separately and need not match in a year (stockpiles, and pipeline gas that fuel receipts do not capture).

Showing 1 of 8 suppliers. Subscribe to see all 8, every one of the 575 deliveries recorded 2011–2023, mine-level origins, transport mode and the delivered price paid — plus sorting, filtering and Excel export.

See all 8 suppliers →

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Associated Electric Coop, Inc
Entity type
Cooperative
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1007746
Balancing authority
AECI
NERC region
SERC
Gas pipeline
Panhandle Eastern Pipeline Company
EIA plant ID
7848

Common questions

How big is Holden Power Plant?
321 MW across 3 generating units in service.
Who owns and operates it?
Owned by Associated Electric Cooperative Inc (100%) and operated by Associated Electric Coop, Inc, filed as cooperative.
Which grid does it sell into?
AECI (Associated Electric Cooperative, Inc.) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 2002. Every operating unit came online in 2002.
When is it due to retire?
No retirement date has been filed for any operating unit at Holden Power Plant. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas. Natural gas and oil & petroleum came from 8 suppliers in 2023.
How much does it spend on fuel?
Its fuel receipts report a delivered cost of $6M in 2023.
How much CO₂ does it emit?
135,920 t in 2023, reported to the EPA — the 1,963rd highest of 6,030 US facilities that reported. Up from 27,828 t in 2011.

Related pages

Missouri energyAll facilities in the state→Empire District Elec Co Energy Ctr379 MW operating capacity→ South Harper Generating Station351 MW operating capacity→ Nodaway Power Plant316 MW operating capacity→ Rock Creek Wind Project300 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming