AMERICAN ENERGY ATLAS
Power·Missouri

Empire District Elec Co Energy Ctr

Sarcoxie, Jasper County, Missouri · SPP · operated by Empire District Electric Co · owned by Liberty Utilities Co

2023 · headline year
Reported fuel cost$9.77M2023 · reported deliveries
Capacity in service379MW4 units · gas
Net generation239GWh2023 · reported
CO₂ emitted173,514t2023 · reported to EPA · 1,667th highest of 6,030 in the US
Rank in Missouri#16of 119 · by capacity · #848 of 13,147 US
Reported suppliersNot reported2023 · last deliveries 2023
Capacity factor7%2023

Location

Jasper County · SPP · MRO

What it burns

2023 · reported

Share of reported fuel consumption

96% Natural gas · 3.07 TBtu · reported4% Oil & petroleum · 0.119 TBtu · reported

Natural gas supplies 96% of the fuel energy it burned in 2023.

CO₂ emitted, t · 2011–2023

0100,000200,000300,000201120172023
Reported (through 2023)

Generating units

4 of 4 shown · 379 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 1129.0Natural GasNatural Gas Fired Combustion Turbine1978Operating
Unit 2129.0Natural GasNatural Gas Fired Combustion Turbine1981Operating
Unit 360.5Natural GasNatural Gas Fired Combustion Turbine2003Operating
Unit 460.5Natural GasNatural Gas Fired Combustion Turbine2003Operating

All 4 units shown. Behind each one, AEA holds the full engineering record: co-firing fuels and fuel-switching times.

See the engineering record →
UnitEventWhenMW
Unit 1retirement2035-12129 MW
Unit 2retirement2035-12129 MW

Who supplies the fuel

2023
No fuel deliveries are reported for 2023. 209 deliveries are on record for 2011–2023.

Delivery history. Subscribe to see every recorded delivery, supplier, mine of origin and transport mode.

See the delivery history →

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
Liberty Utilities Co · 100%
Operating utility
Empire District Electric Co
Entity type
Investor-Owned Utility
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1001046
Balancing authority
SPP
NERC region
MRO
Gas pipeline
Southern Star Central Gas Pipeline
EIA plant ID
6223

Common questions

How big is Empire District Elec Co Energy Ctr?
379 MW across 4 generating units in service.
Who owns and operates it?
Owned by Liberty Utilities Co (100%) and operated by Empire District Electric Co, filed as investor-owned utility.
Which grid does it sell into?
SPP (Southwest Power Pool) is its balancing authority, inside NERC's MRO region.
How old is it?
The capacity-weighted average megawatt here came online in 1987. The oldest operating unit is Unit 1 (1978); the newest are Unit 3 and Unit 4 (2003).
When is it due to retire?
Planned retirement dates are filed for 2 of 4 operating units: Unit 1 (2035) and Unit 2 (2035).
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas and oil & petroleum.
How much does it spend on fuel?
Its fuel receipts report a delivered cost of $9.77M in 2023.
How much CO₂ does it emit?
173,514 t in 2023, reported to the EPA — the 1,667th highest of 6,030 US facilities that reported. Up from 41,545 t in 2011.

Related pages

Missouri energyAll facilities in the state→Taum Sauk408 MW operating capacity→ High Prairie Wind Farm400 MW operating capacity→ South Harper Generating Station351 MW operating capacity→ Holden Power Plant321 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming