Haynes Generating Station

Long Beach, Los Angeles County, California · LDWP · operated by Los Angeles Department of Water & Power · owned by City of Los Angeles California

2023 · headline year
Reported fuel cost$177M2023 · reported deliveries
Capacity in service1,739MW11 units · gas
Net generation2.55TWh2023 · reported
CO₂ emitted1.08Mt2023 · reported to EPA · 561st highest of 6,030 in the US
Rank in California#4of 1,713 · by capacity · #110 of 13,147 US
Reported suppliers12023 · 12 deliveries
Capacity factor17%2023

Location

Los Angeles County · LDWP · WECC

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 20.2 TBtu · reported

CO₂ emitted, Mt · 2011–2023

00.511.5201120172023
Reported (through 2023)

Generating units

15 of 15 shown · 1,739 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 8264.3Natural GasNatural Gas Fired Combined Cycle2005Operating
Unit 1230.0Natural GasNatural Gas Steam Turbine1962Operating
Unit 2230.0Natural GasNatural Gas Steam Turbine1963Operating
Unit 10182.8Natural GasNatural Gas Fired Combined Cycle2005Operating
Unit 9182.8Natural GasNatural Gas Fired Combined Cycle2005Operating
Unit 11108.2Natural GasNatural Gas Fired Combustion Turbine2013Operating
Unit 12108.2Natural GasNatural Gas Fired Combustion Turbine2013Operating
Unit 13108.2Natural GasNatural Gas Fired Combustion Turbine2013Operating
Unit 14108.2Natural GasNatural Gas Fired Combustion Turbine2013Operating
Unit 15108.2Natural GasNatural Gas Fired Combustion Turbine2013Operating
Unit 16108.2Natural GasNatural Gas Fired Combustion Turbine2013Operating
Unit 5343.0Natural GasNatural Gas Steam Turbine1966Retired 2013
Unit 6343.0Natural GasNatural Gas Steam Turbine1967Retired 2013
Unit 3230.0Natural GasNatural Gas Steam Turbine1964Retired 2004
Unit 4230.0Natural GasNatural Gas Steam Turbine1965Retired 2003

All 15 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; co-firing fuels and fuel-switching times; NOₓ, particulate and mercury controls with compliance years; cooling system and water source with withdrawal rate; stack height.

See the engineering record →

Who supplies the fuel

1 of 1 supplier · delivered in 2023
SupplierFuelDelivered TBtuTonsMine of originTransport
Southern California GasNatural gas20.3n/an/aPipeline

Figures are volumes delivered in 2023, not volumes burned. Tons are shown for coal only.

The supplier is shown. Subscribe to see every one of the 156 deliveries recorded 2011–2023, mine-level origins, transport mode and the delivered price paid — plus sorting, filtering and Excel export.

See the delivery history →

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
City of Los Angeles California · 100%
Operating utility
Los Angeles Department of Water & Power
Entity type
Municipally Owned Utility
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1006097
Balancing authority
LDWP
NERC region
WECC
EIA plant ID
400

Common questions

How big is Haynes Generating Station?
1,739 MW across 11 generating units in service. A further 4 units are listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Owned by City of Los Angeles California (100%) and operated by Los Angeles Department of Water & Power, filed as municipally owned utility.
Which grid does it sell into?
LDWP (Los Angeles Department of Water and Power) is its balancing authority, inside NERC's WECC region.
How old is it?
The capacity-weighted average megawatt here came online in 1997. The oldest operating unit is Unit 1 (1962); the newest are Unit 11, Unit 12, Unit 13, Unit 14 and 2 more (2013).
When is it due to retire?
No retirement date has been filed for any operating unit at Haynes Generating Station. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas. Natural gas came from 1 supplier in 2023.
How much does it spend on fuel?
Its fuel receipts report a delivered cost of $177M in 2023.
How much CO₂ does it emit?
1.08 Mt in 2023, reported to the EPA — the 561st highest of 6,030 US facilities that reported. Down from 1.31 Mt in 2011.

Related pages

California energyAll facilities in the state→Moss Landing2,148 MW operating capacity→ AES Alamitos1,793 MW operating capacity→ Castaic1,682 MW operating capacity→ Ormond Beach Power, LLC1,612 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming