San Diego County, California · CAISO · operated by EnerSmart Storage
Capacity shown is planned or not in service
A planned 18.0 MW batteries project, filed to come online in 2026.
| Unit | Capacity MW | Fuel | Technology | Online | Status |
|---|---|---|---|---|---|
| Unit M01 | 3.0 | Storage | Batteries | 2026 | Proposed |
| Unit M02 | 3.0 | Storage | Batteries | 2026 | Proposed |
| Unit M03 | 3.0 | Storage | Batteries | 2026 | Proposed |
| Unit M04 | 3.0 | Storage | Batteries | 2026 | Proposed |
| Unit M05 | 3.0 | Storage | Batteries | 2026 | Proposed |
| Unit M06 | 3.0 | Storage | Batteries | 2026 | Proposed |
| Unit M07 | 3.0 | Storage | Batteries | not reported | Canceled |
All 7 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.
See the engineering record →| Unit | Event | When | MW |
|---|---|---|---|
| Unit M01 | new unit | 2026 | 3.0 MW |
| Unit M02 | new unit | 2026 | 3.0 MW |
| Unit M03 | new unit | 2026 | 3.0 MW |
| Unit M04 | new unit | 2026 | 3.0 MW |
| Unit M05 | new unit | 2026 | 3.0 MW |
| Unit M06 | new unit | 2026 | 3.0 MW |