AMERICAN ENERGY ATLAS
Power·Virginia

Electric Avenue Facility

Culpeper County, Virginia · PJM · operated by Town of Culpeper- (VA)

2023 · headline year
Fuel spend$120,0152023 · estimate
Capacity in service6.9MW4 units · oil
Net generation480MWh2023 · reported
Rank in Virginia#154of 230 · by capacity · #6,179 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor1%2023

Location

Culpeper County · PJM · SERC

What it burns

2023 · reported

Share of reported fuel consumption

100% Oil & petroleum · 6,088 MMBtu · reported · $120,015 est.

Reported fuel consumption, MMBtu · 2011–2023

02,5005,0007,500201120172023
Reported (through 2023)

Generating units

4 of 4 shown · 6.9 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 11.8Distillate oilPetroleum Liquids2004Operating
Unit 21.8Distillate oilPetroleum Liquids2004Operating
Unit 31.8Distillate oilPetroleum Liquids2004Operating
Unit 41.5Distillate oilPetroleum Liquids1997Operating

All 4 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Town of Culpeper- (VA)
Entity type
Municipally Owned Utility
Regulatory status
Regulated
Balancing authority
PJM
NERC region
SERC
EIA plant ID
56367

Common questions

How big is Electric Avenue Facility?
6.9 MW across 4 generating units in service.
Who owns and operates it?
Operated by Town of Culpeper- (VA), filed as municipally owned utility.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 2002. The oldest operating unit is Unit 4 (1997); the newest are Unit 1, Unit 2 and Unit 3 (2004).
When is it due to retire?
No retirement date has been filed for any operating unit at Electric Avenue Facility. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned oil & petroleum.
How much does it spend on fuel?
An estimated $120,015 in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.

Related pages

Virginia energyAll facilities in the state→GP Big Island, LLC7.9 MW operating capacity→ Cushaw7.5 MW operating capacity→ Middle Peninsula Landfill6.4 MW operating capacity→ Richmond Energy6.4 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming