Parlin, Middlesex County, New Jersey · PJM · operated by Consolidated Edison Energy, Inc. · owned by General Electric Co
Generating units retired 20232023 · headline year
Retired — its last generating unit went out of service in 2023, ending 135 MW of capacity, 100% natural gas by fuel energy in 2023.
Fuel spend$264,2772023 · estimate
Retired capacity135MW4 units · none in service
CO₂ emitted4,639t2023 · reported to EPA · 5,900th highest of 6,030 in the US
Rank in New Jersey#76of 78 · by reported CO₂ · #5,900 of 6,030 US
Reported suppliersNot reported2023 · last deliveries 2012
Location
What it burns
2023 · reported
Share of reported fuel consumption
100% Natural gas · 85,980 MMBtu · reported · $264,277 est.
CO₂ emitted, t · 2011–2023
Reported (through 2023)
Generating units
4 of 4 shown · none in service
Unit
Capacity MW
Fuel
Technology
Online
Status
Unit GEN1
45.9
Natural Gas
Natural Gas Fired Combined Cycle
1991
Retired 2023
Unit GEN2
45.9
Natural Gas
Natural Gas Fired Combined Cycle
1991
Retired 2023
Unit GEN3
21.6
Natural Gas
Natural Gas Fired Combined Cycle
1991
Retired 2023
Unit GEN4
21.6
Natural Gas
Natural Gas Fired Combined Cycle
1991
Retired 2023
All 4 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; NOₓ, particulate and mercury controls with compliance years; stack height; ownership stakes where a unit is jointly held.