AMERICAN ENERGY ATLAS
Power·Kentucky

D B Wilson

Island, Ohio County, Kentucky · MISO · operated by Big Rivers Electric Corp · owned by Big Rivers Electric Corp

2023 · headline year
Reported fuel cost$67.6M2023 · reported deliveries
Capacity in service509MW1 unit · coal
Net generation2.9TWh2023 · reported
CO₂ emitted3.22Mt2023 · reported to EPA · 145th highest of 6,030 in the US
Rank in Kentucky#14of 58 · by capacity · #695 of 13,147 US
Reported suppliers52023 · 64 deliveries
Capacity factor65%2023

Location

Ohio County · MISO · SERC

What it burns

2023 · reported

Share of reported fuel consumption

100% Coal · 31.4 TBtu · reported

CO₂ emitted, Mt · 2011–2023

0246201120172023
Reported (through 2023)

Generating units

1 of 1 shown · 509 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 1509.4Bituminous coalConventional Steam Coal1984Operating

1 unit shown. Behind it, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; co-firing fuels and fuel-switching times; SO₂ scrubber type, sorbent and removal efficiency; NOₓ, particulate and mercury controls with compliance years; cooling system and water source with withdrawal rate; stack height.

See the engineering record →

Who supplies the fuel

1 of 5 suppliers · delivered in 2023
SupplierFuelDelivered TBtuTonsMine of originTransport
American Consolidated Natural Resources Coal SalesCoal15637,921Paradise #9, KentuckyTruck

Figures are volumes delivered in 2023, not volumes burned. Tons are shown for coal only.

Showing 1 of 5 suppliers. Subscribe to see all 5, every one of the 786 deliveries recorded 2011–2023, mine-level origins, transport mode and the delivered price paid — plus sorting, filtering and Excel export.

See all 5 suppliers →

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
Big Rivers Electric Corp · 100%
Operating utility
Big Rivers Electric Corp
Entity type
Cooperative
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1001066
Balancing authority
MISO
NERC region
SERC
EIA plant ID
6823

Common questions

How big is D B Wilson?
509 MW across 1 generating unit in service.
Who owns and operates it?
Owned by Big Rivers Electric Corp (100%) and operated by Big Rivers Electric Corp, filed as cooperative.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 1984.
When is it due to retire?
No retirement date has been filed for any operating unit at D B Wilson. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned coal. Coal delivered in 2023 came from 3 coal suppliers, from mines in Kentucky — principally Paradise #9. Other fuels (oil & petroleum) came from 2 suppliers in 2023.
How much does it spend on fuel?
Its fuel receipts report a delivered cost of $67.6M in 2023.
How much CO₂ does it emit?
3.22 Mt in 2023, reported to the EPA — the 145th highest of 6,030 US facilities that reported. Down from 3.47 Mt in 2011.

Related pages

Kentucky energyAll facilities in the state→Bluegrass Generating Station624 MW operating capacity→ R D Green586 MW operating capacity→ John S. Cooper344 MW operating capacity→ Big Sandy280 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming