Leesburg, Lake County, Florida · FPC · operated by Cutrale Citrus Juices USA Inc · owned by Cutrale Citrus Juices USA Inc

2023 · headline year
Fuel spend$2.93M2023 · estimate
Capacity in service4.1MW1 unit · gas
Net generation24.5GWh2023 · reported
CO₂ emitted22,318t2023 · reported to EPA · 5,321st highest of 6,030 in the US
Rank in Florida#278 (tied)of 310 · by capacity · #8,013 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor68%2023

Location

Lake County · FPC · SERC

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 398,911 MMBtu · reported · $2.93M est.

CO₂ emitted, t · 2011–2023

020,00040,00060,000201120172023
Reported (through 2023)

Generating units

3 of 3 shown · 4.1 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit GEN34.1Natural GasNatural Gas Fired Combustion Turbine2016Operating
Unit GEN24.1Natural GasNatural Gas Fired Combustion Turbine2010Retired 2016
Unit GEN13.5Natural GasNatural Gas Fired Combustion Turbine1987Retired 2010

All 3 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
Cutrale Citrus Juices USA Inc · 100%
Operating utility
Cutrale Citrus Juices USA Inc
Entity type
Industrial
Regulatory status
Not Regulated
Industry sector
Other
EPA facility ID
1006667
Balancing authority
FPC
NERC region
SERC
Gas pipeline
Florida Gas Transmission Company
EIA plant ID
10020

Common questions

How big is Cutrale Citrus Juices USA, Inc.?
4.1 MW across 1 generating unit in service. A further 2 units are listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Owned by Cutrale Citrus Juices USA Inc (100%) and operated by Cutrale Citrus Juices USA Inc, filed as industrial.
Which grid does it sell into?
FPC (Progress Energy Florida) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 2016.
When is it due to retire?
No retirement date has been filed for any operating unit at Cutrale Citrus Juices USA, Inc. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas.
How much does it spend on fuel?
An estimated $2.93M in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
How much CO₂ does it emit?
22,318 t in 2023, reported to the EPA — the 5,321st highest of 6,030 US facilities that reported. Down from 40,334 t in 2011.

Related pages

Florida energyAll facilities in the state→Central District Wastewater Treat Plant4.8 MW operating capacity→ Seminole Energy4.8 MW operating capacity→ ACE-Stanton A PV4.1 MW operating capacity→ Naples Landfill4.0 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming