The 2nd-largest power plant in Nevada by capacity — 1,376 MW, 100% natural gas by fuel energy in 2023, first unit online in 1973, newest in 2008.

Reported fuel cost$24.4M2023 · reported deliveries
Capacity in service1,376MW19 units · gas
Net generation571GWh2023 · reported
CO₂ emitted309,091t2023 · reported to EPA · 1,218th highest of 6,030 in the US
Rank in Nevada#2of 111 · by capacity · #172 of 13,147 US
Reported suppliers12023 · 12 deliveries
Capacity factor5%2023

Location

Clark County · NEVP · WECC

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 5.7 TBtu · reported

CO₂ emitted, t · 2011–2023

0200,000400,000600,000201120172023
Reported (through 2023)

Generating units

22 of 22 shown · 1,376 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 10104.4Natural GasNatural Gas Fired Combined Cycle1994Operating
Unit 9104.4Natural GasNatural Gas Fired Combined Cycle1993Operating
Unit GT592.5Natural GasNatural Gas Fired Combined Cycle1979Operating
Unit GT692.5Natural GasNatural Gas Fired Combined Cycle1979Operating
Unit GT792.5Natural GasNatural Gas Fired Combined Cycle1980Operating
Unit GT892.5Natural GasNatural Gas Fired Combined Cycle1982Operating
Unit GT472.4Natural GasNatural Gas Fired Combustion Turbine1973Operating
Unit 1160.5Natural GasNatural Gas Fired Combustion Turbine2008Operating
Unit 1260.5Natural GasNatural Gas Fired Combustion Turbine2008Operating
Unit 1360.5Natural GasNatural Gas Fired Combustion Turbine2008Operating
Unit 1460.5Natural GasNatural Gas Fired Combustion Turbine2008Operating
Unit 1560.5Natural GasNatural Gas Fired Combustion Turbine2008Operating
Unit 1660.5Natural GasNatural Gas Fired Combustion Turbine2008Operating
Unit 1760.5Natural GasNatural Gas Fired Combustion Turbine2008Operating
Unit 1860.5Natural GasNatural Gas Fired Combustion Turbine2008Operating
Unit 1960.5Natural GasNatural Gas Fired Combustion Turbine2008Operating
Unit 2060.5Natural GasNatural Gas Fired Combustion Turbine2008Operating
Unit 2260.5Natural GasNatural Gas Fired Combustion Turbine2008Operating
Unit 2158.9Natural GasNatural Gas Fired Combustion Turbine2008Operating
Unit 375.0Natural GasNatural Gas Steam Turbine1961Retired 2005
Unit 265.0Natural GasNatural Gas Steam Turbine1957Retired 2005
Unit 150.0Natural GasNatural Gas Steam Turbine1955Retired 2005

All 22 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; NOₓ, particulate and mercury controls with compliance years; cooling system and water source with withdrawal rate; stack height.

See the engineering record →

Who supplies the fuel

1 of 1 supplier · delivered in 2023
SupplierFuelDelivered TBtuTonsMine of originTransport
Southwest GasNatural gas5.88n/an/aPipeline

Figures are volumes delivered in 2023, not volumes burned. Tons are shown for coal only.

The supplier is shown. Subscribe to see every one of the 156 deliveries recorded 2011–2023, mine-level origins, transport mode and the delivered price paid — plus sorting, filtering and Excel export.

See the delivery history →

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
Berkshire Hathaway Inc · 100%
Operating utility
Nevada Power Co
Entity type
Investor-Owned Utility
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1000726
Balancing authority
NEVP
NERC region
WECC
Gas pipeline
Southwest Gas Corporation
EIA plant ID
2322

Common questions

How big is Clark?
1,376 MW across 19 generating units in service. A further 3 units are listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Owned by Berkshire Hathaway Inc (100%) and operated by Nevada Power Co, filed as investor-owned utility.
Which grid does it sell into?
NEVP (Nevada Power Company) is its balancing authority, inside NERC's WECC region.
How old is it?
The capacity-weighted average megawatt here came online in 1996. The oldest operating unit is Unit GT4 (1973); the newest are Unit 11, Unit 12, Unit 13, Unit 14 and 8 more (2008).
When is it due to retire?
No retirement date has been filed for any operating unit at Clark. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas. Natural gas came from 1 supplier in 2023.
How much does it spend on fuel?
Its fuel receipts report a delivered cost of $24.4M in 2023.
How much CO₂ does it emit?
309,091 t in 2023, reported to the EPA — the 1,218th highest of 6,030 US facilities that reported. Up from 159,978 t in 2011.

Related pages

Nevada energyAll facilities in the state→Chuck Lenzie Generating Station1,466 MW operating capacity→ Silverhawk1,120 MW operating capacity→ Gemini Solar Hybrid1,070 MW operating capacity→ Hoover Dam (NV)1,039 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming