Figures are volumes delivered in 2023, not volumes burned. Tons are shown for coal only.
The supplier is shown. Subscribe to see every one of the 288 deliveries recorded 2011–2023, mine-level origins, transport mode and the delivered price paid — plus sorting, filtering and Excel export.
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 2002. The oldest operating units are Unit SN01 and Unit SN02 (1999); the newest is Unit SN07 (2007).
When is it due to retire?
No retirement date has been filed for any operating unit at City Water & Light - City of Jonesboro. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas. Natural gas came from 1 supplier in 2023.
How much does it spend on fuel?
Its fuel receipts report a delivered cost of $2.17M in 2023.
How much CO₂ does it emit?
51,100 t in 2023, reported to the EPA — the 3,651st highest of 6,030 US facilities that reported. Down from 141,234 t in 2011.