AMERICAN ENERGY ATLAS
Power·California

Blacksand Generating Facility

Orange County, California · CAISO · operated by Bridge Energy LLC

2023 · headline year
Fuel spend$10.1M2023 · estimate
Capacity in service8.0MW3 units · gas
Net generation45.1GWh2023 · reported
Rank in California#794 (tied)of 1,713 · by capacity · #5,917 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor64%2023

Location

Orange County · CAISO · WECC

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 738,606 MMBtu · reported · $10.1M est.

Reported fuel consumption, MMBtu · 2011–2023

0300,000600,000900,000201120172023
Reported (through 2023)

Generating units

5 of 5 shown · 8.0 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit D1824.0Natural GasNatural Gas Fired Combustion Turbine2000Operating
Unit D1893.7Natural GasNatural Gas Fired Combustion Turbine2000Operating
Unit D1900.3Natural GasNatural Gas Fired Combustion Turbine2012Operating
Unit D1910.8Natural GasNatural Gas Fired Combustion Turbine2025Proposed
Unit D1920.8Natural GasNatural Gas Fired Combustion Turbine2025Proposed

All 5 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →
UnitEventWhenMW
Unit D191new unit20250.8 MW
Unit D192new unit20250.8 MW

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Bridge Energy LLC
Entity type
Industrial
Regulatory status
Not Regulated
Balancing authority
CAISO
NERC region
WECC
EIA plant ID
56090

Common questions

How big is Blacksand Generating Facility?
8.0 MW across 3 generating units in service. A further 2 units are listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Operated by Bridge Energy LLC, filed as industrial.
Which grid does it sell into?
CAISO (California Independent System Operator) is its balancing authority, inside NERC's WECC region.
How old is it?
The capacity-weighted average megawatt here came online in 2000. The oldest operating units are Unit D182 and Unit D189 (2000); the newest is Unit D190 (2012).
When is it due to retire?
No retirement date has been filed for any operating unit at Blacksand Generating Facility. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas.
How much does it spend on fuel?
An estimated $10.1M in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.

Related pages

California energyAll facilities in the state→Chili Bar8.3 MW operating capacity→ Bishop Creek 48.2 MW operating capacity→ C&H Sugar Plant8.0 MW operating capacity→ Orion Solar II8.0 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming