Fuel spend$7,1422023 · estimate
Capacity in service6.0MW3 units · oil
Net generation14MWh2023 · reported
Rank in Minnesota#164 (tied)of 767 · by capacity · #6,337 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor0%2023
How big is Willmar Municipal SW Substation?
6.0 MW across 3 generating units in service.
Who owns and operates it?
Operated by Willmar Municipal Utilities, filed as municipally owned utility.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's MRO region.
How old is it?
The capacity-weighted average megawatt here came online in 2000. Every operating unit came online in 2000.
When is it due to retire?
No retirement date has been filed for any operating unit at Willmar Municipal SW Substation. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned oil & petroleum.
How much does it spend on fuel?
An estimated $7,142 in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.