AMERICAN ENERGY ATLAS
Industrial + power·Virginia

WestRock Virginia, Covington

Covington, Alleghany County, Virginia · PJM · operated by WestRock Corp · owned by Westrock Co

2023 · headline year
Fuel spend$62.9M2023 · estimate
Capacity in service161MW4 units · biomass + coal
Net generation663GWh2023 · reported
CO₂ emitted970,084t2023 · reported to EPA · 613th highest of 6,030 in the US
Rank in Virginia#30of 230 · by capacity · #1,751 of 13,147 US
Reported suppliers52023 · 41 deliveries
Capacity factor47%2023

Location

Alleghany County · PJM · SERC

What its on-site power plant burns

2023 · reported

Share of reported fuel consumption

61% Black liquor · 17.2 TBtu · reported27% Natural gas · 7.5 TBtu · reported · $38.9M est.11% Coal · 3.18 TBtu · reported · $20.4M est.1% Oil & petroleum · 0.236 TBtu · reported · $3.6M est.

Black liquor supplies 61% of the fuel energy its on-site power plant burned in 2023.

CO₂ emitted, Mt · 2011–2023

0123201120172023
Reported (through 2023)

Generating units

7 of 7 shown · 161 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit GEN782.4WoodWood/Wood Waste Biomass2013Operating
Unit GEN434.0Black liquorWood/Wood Waste Biomass1980Operating
Unit GEN534.0Bituminous coalConventional Steam Coal1989Operating
Unit GEN310.5Bituminous coalConventional Steam Coal1951Operating
Unit GEN110.5Bituminous coalConventional Steam Coal1939Retired 2013
Unit GEN210.5Bituminous coalConventional Steam Coal1946Retired 2013
Unit GEN65.5Black liquorWood/Wood Waste Biomass1930Retired 2009

All 7 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; co-firing fuels and fuel-switching times; SO₂ scrubber type, sorbent and removal efficiency; NOₓ, particulate and mercury controls with compliance years; stack height.

See the engineering record →

Who supplies the fuel

1 of 5 suppliers · delivered in 2023
SupplierFuelDelivered TBtuTonsMine of originTransport
Columbia GasNatural gas7.5n/an/aPipeline

Figures are volumes delivered in 2023, not volumes burned. Tons are shown for coal only.

Showing 1 of 5 suppliers. Subscribe to see all 5, every one of the 756 deliveries recorded 2011–2023, mine-level origins, transport mode and the delivered price paid — plus sorting, filtering and Excel export.

See all 5 suppliers →

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
Westrock Co · 100%
Operating utility
WestRock Corp
Entity type
Industrial
Regulatory status
Not Regulated
Industry sector
Pulp and Paper, Waste
EPA facility ID
1000256
Balancing authority
PJM
NERC region
SERC
EIA plant ID
50900

Common questions

How big is WestRock Virginia, Covington?
161 MW across 4 generating units in service — 116 MW of biomass and 44.5 MW of coal. A further 3 units are listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Owned by Westrock Co (100%) and operated by WestRock Corp, filed as industrial.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 1997. The oldest operating unit is Unit GEN3 (1951); the newest is Unit GEN7 (2013).
When is it due to retire?
No retirement date has been filed for any operating unit at WestRock Virginia, Covington. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 its on-site power plant burned black liquor, natural gas, coal and oil & petroleum. Coal delivered in 2023 came from 2 coal suppliers, from mines in Kentucky — principally Manchester Tipple. Other fuels (natural gas and oil & petroleum) came from 3 suppliers in 2023.
How much does it spend on fuel?
An estimated $62.9M in 2023 — natural gas $38.9M, coal $20.4M and oil & petroleum $3.6M. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
How much CO₂ does it emit?
970,084 t in 2023, reported to the EPA — the 613th highest of 6,030 US facilities that reported. Down from 1.71 Mt in 2011.

Related pages

Virginia energyAll facilities in the state→Skipjack Solar Center175 MW operating capacity→ Highlander Solar Energy Station 1165 MW operating capacity→ Cavalier Solar156 MW operating capacity→ Fort Powhatan Solar150 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming