AMERICAN ENERGY ATLAS
Power·Georgia

Wansley (7946)

Franklin, Heard County, Georgia · SOCO · operated by Municipal Electric Authority · owned by Municipal Electric Authority of Georgia

2023 · headline year
Reported fuel cost$62.8M2023 · reported deliveries
Capacity in service594MW3 units · gas
Net generation2.97TWh2023 · reported
CO₂ emitted1.15Mt2023 · reported to EPA · 527th highest of 6,030 in the US
Rank in Georgia#19of 247 · by capacity · #593 of 13,147 US
Reported suppliers12023 · 34 deliveries
Capacity factor57%2023

Location

Heard County · SOCO · SERC

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 21.5 TBtu · reported

CO₂ emitted, Mt · 2011–2023

00.511.5201120172023
Reported (through 2023)

Generating units

3 of 3 shown · 594 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit ST1226.9Natural GasNatural Gas Fired Combined Cycle2004Operating
Unit CT1183.6Natural GasNatural Gas Fired Combined Cycle2004Operating
Unit CT2183.6Natural GasNatural Gas Fired Combined Cycle2004Operating

All 3 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; NOₓ, particulate and mercury controls with compliance years; cooling system and water source with withdrawal rate; stack height.

See the engineering record →

Who supplies the fuel

1 of 1 supplier · delivered in 2023
SupplierFuelDelivered TBtuTonsMine of originTransport
TranscoNatural gas21.5n/an/aPipeline

Figures are volumes delivered in 2023, not volumes burned. Tons are shown for coal only.

The supplier is shown. Subscribe to see every one of the 301 deliveries recorded 2011–2023, mine-level origins, transport mode and the delivered price paid — plus sorting, filtering and Excel export.

See the delivery history →

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Municipal Electric Authority
Entity type
Municipally Owned Utility
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1007100
Balancing authority
SOCO
NERC region
SERC
Gas pipeline
Transcontinental Gas Pipeline
EIA plant ID
7946

Common questions

How big is Wansley (7946)?
594 MW across 3 generating units in service.
Who owns and operates it?
Owned by Municipal Electric Authority of Georgia (100%) and operated by Municipal Electric Authority, filed as municipally owned utility.
Which grid does it sell into?
SOCO (Southern Company Services, Inc. - Trans) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 2004. Every operating unit came online in 2004.
When is it due to retire?
No retirement date has been filed for any operating unit at Wansley (7946). An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas. Natural gas came from 1 supplier in 2023.
How much does it spend on fuel?
Its fuel receipts report a delivered cost of $62.8M in 2023.
How much CO₂ does it emit?
1.15 Mt in 2023, reported to the EPA — the 527th highest of 6,030 US facilities that reported. Up from 504,271 t in 2011.

Related pages

Georgia energyAll facilities in the state→AL Sandersville692 MW operating capacity→ Bobby C. Smith Jr. Energy Facility597 MW operating capacity→ Sewell Creek Energy570 MW operating capacity→ McManus560 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming