A planned 2.3 MW solar photovoltaic project, filed to come online in 2025.

Planned capacity2.3MW1 unit · not yet in service

Location

Whiteside County · MISO · SERC

Generating units

1 of 1 shown · none in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit USCAT2.3SolarSolar Photovoltaic2025Proposed

1 unit shown. Behind it, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →
UnitEventWhenMW
Unit USCATnew unit20252.3 MW

Ownership & operations

Operating utility
USS Cattail Solar LLC
Entity type
Independent Power Producer
Regulatory status
Not Regulated
Balancing authority
MISO
NERC region
SERC
EIA plant ID
68755

Common questions

How big is USS Cattail Solar?
2.3 MW across 1 unit, none of which is in service — all planned.
Who owns and operates it?
Operated by USS Cattail Solar LLC, filed as independent power producer.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's SERC region.
What does it run on?
Solar Photovoltaic (2.3 MW).

Related pages

Illinois energyAll facilities in the state→Upper Rock Energy Partners LLCPower facility→ USS Beard SolarPower facility→ USS Ducks SolarPower facility→ USS Grandpa SolarPower facility→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming