AMERICAN ENERGY ATLAS
Industrial + power·Pennsylvania

US Steel (Clairton Coke)

Clairton, Allegheny County, Pennsylvania · PJM · operated by United States Steel- Clairton · owned by US Steel Corp

2023 · headline year
Capacity in service31.0MW2 units · gas
Net generation109GWh2023 · reported
CO₂ emitted769,566t2023 · reported to EPA · 734th highest of 6,030 in the US
Rank in Pennsylvania#109of 256 · by capacity · #3,990 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor40%2023

Location

Allegheny County · PJM · RFC

What its on-site power plant burns

2023 · reported

Share of reported fuel consumption

95% Refinery gas · 6.27 TBtu · reported5% Natural gas · 0.299 TBtu · reported

Refinery gas supplies 95% of the fuel energy its on-site power plant burned in 2023.

CO₂ emitted, t · 2011–2023

0500,0001,000,0001,500,000201120172023
Reported (through 2023)

Generating units

2 of 2 shown · 31.0 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit GEN121.0Other gasOther Gases1955Operating
Unit GEN310.0Other gasOther Gases1955Operating

All 2 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; NOₓ, particulate and mercury controls with compliance years.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
US Steel Corp · 100%
Operating utility
United States Steel- Clairton
Entity type
Industrial
Regulatory status
Not Regulated
Industry sector
Metals
EPA facility ID
1000124
Balancing authority
PJM
NERC region
ReliabilityFirst (RFC)
EIA plant ID
50729

Common questions

How big is US Steel (Clairton Coke)?
31.0 MW across 2 generating units in service.
Who owns and operates it?
Owned by US Steel Corp (100%) and operated by United States Steel- Clairton, filed as industrial.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's ReliabilityFirst region.
How old is it?
The capacity-weighted average megawatt here came online in 1955. Every operating unit came online in 1955.
When is it due to retire?
No retirement date has been filed for any operating unit at US Steel (Clairton Coke). An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 its on-site power plant burned refinery gas and natural gas.
How much CO₂ does it emit?
769,566 t in 2023, reported to the EPA — the 734th highest of 6,030 US facilities that reported. Up from 649,300 t in 2011.

Related pages

Pennsylvania energyAll facilities in the state→Casselman Wind Power Project34.5 MW operating capacity→ Covanta Plymouth Renewable Energy LLC32.1 MW operating capacity→ Meyersdale Windpower, LLC30.0 MW operating capacity→ Patton Wind Farm30.0 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming