AMERICAN ENERGY ATLAS
Power·Illinois

Trenton East Phase 2

Clinton County, Illinois

2023 · headline year
Capacity in service2.0MW1 unit · solar · incl. 2.0 MW online after 2023
Rank in Illinois#228 (tied)of 433 · by capacity · #9,808 (tied) of 13,147 US

Location

Clinton County

Generating units

1 of 1 shown · 2.0 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 111432.0SolarSolar Photovoltaic2025Operating

1 unit shown. Behind it, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Ownership & operations

EIA plant ID
69598

Common questions

How big is Trenton East Phase 2?
2.0 MW across 1 generating unit in service.
How old is it?
The capacity-weighted average megawatt here came online in 2025.
When is it due to retire?
No retirement date has been filed for any operating unit at Trenton East Phase 2. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it run on?
Solar Photovoltaic (2.0 MW).

Related pages

Illinois energyAll facilities in the state→Tower Road Solar, LLC CSG2.0 MW operating capacity→ Trenton East2.0 MW operating capacity→ Trenton West2.0 MW operating capacity→ Trenton West Phase 22.0 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming