AMERICAN ENERGY ATLAS
Power·California

Tracy Linne

San Joaquin County, California

2023 · headline year
Capacity in service2.7MW2 units · solar + storage · incl. 2.7 MW online after 2023
Rank in California#1,144 (tied)of 1,713 · by capacity · #9,246 (tied) of 13,147 US

Location

San Joaquin County

Generating units

2 of 2 shown · 2.7 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit LINS1.4SolarSolar Photovoltaic2026Operating
Unit LINB1.3StorageBatteries2026Operating

All 2 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Ownership & operations

EIA plant ID
69759

Common questions

How big is Tracy Linne?
2.7 MW across 2 generating units in service — 1.4 MW of solar and 1.3 MW of storage.
How old is it?
The capacity-weighted average megawatt here came online in 2026. Every operating unit came online in 2026.
When is it due to retire?
No retirement date has been filed for any operating unit at Tracy Linne. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it run on?
Solar Photovoltaic (1.4 MW) and Batteries (1.3 MW).

Related pages

California energyAll facilities in the state→Parker2.7 MW operating capacity→ San Antonio Regional Hospital2.7 MW operating capacity→ Warm Springs Hydro Project2.7 MW operating capacity→ 20333 Normandie PV, LLC2.6 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming