Maricopa County, Arizona · SRP · operated by Sun Pond, LLC
Capacity shown is planned or not in service
A planned 170 MW solar photovoltaic project, filed to come online in 2026.
| Unit | Capacity MW | Fuel | Technology | Online | Status |
|---|---|---|---|---|---|
| Unit GEN01 | 85.0 | Solar | Solar Photovoltaic | 2026 | Proposed |
| Unit GEN02 | 85.0 | Storage | Batteries | 2026 | Proposed |
All 2 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.
See the engineering record →| Unit | Event | When | MW |
|---|---|---|---|
| Unit GEN01 | new unit | 2026 | 85.0 MW |