AMERICAN ENERGY ATLAS
Power·South Carolina

Seneca City of

Oconee County, South Carolina · DUK · operated by City of Seneca - (SC)

2023 · headline year
Fuel spend$204,2792023 · estimate
Capacity in service10.0MW5 units · oil
Net generation1GWh2023 · reported
Rank in South Carolina#83 (tied)of 204 · by capacity · #5,369 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor1%2023

Location

Oconee County · DUK · SERC

What it burns

2023 · reported

Share of reported fuel consumption

100% Oil & petroleum · 9,167 MMBtu · reported · $204,279 est.

Reported fuel consumption, MMBtu · 2011–2023

010,00020,00030,000201120172023
Reported (through 2023)

Generating units

5 of 5 shown · 10.0 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit PPG12.0Distillate oilPetroleum Liquids2004Operating
Unit PPG22.0Distillate oilPetroleum Liquids2004Operating
Unit PPG32.0Distillate oilPetroleum Liquids2004Operating
Unit WPG12.0Distillate oilPetroleum Liquids2004Operating
Unit WPG22.0Distillate oilPetroleum Liquids2004Operating

All 5 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
City of Seneca - (SC)
Entity type
Municipally Owned Utility
Regulatory status
Regulated
Balancing authority
DUK
NERC region
SERC
EIA plant ID
56545

Common questions

How big is Seneca City of?
10.0 MW across 5 generating units in service.
Who owns and operates it?
Operated by City of Seneca - (SC), filed as municipally owned utility.
Which grid does it sell into?
DUK (Duke Energy Carolinas) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 2004. Every operating unit came online in 2004.
When is it due to retire?
No retirement date has been filed for any operating unit at Seneca City of. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned oil & petroleum.
How much does it spend on fuel?
An estimated $204,279 in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.

Related pages

South Carolina energyAll facilities in the state→Rankin Solar Center, LLC10.0 MW operating capacity→ Ridgeland Solar Project10.0 MW operating capacity→ Sunflower Solar LLC10.0 MW operating capacity→ Whitetail Solar10.0 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming