AMERICAN ENERGY ATLAS
Power·Oregon

Seaside BESS

Multnomah County, Oregon · PGE · operated by Portland General Electric Co

Capacity shown is planned or not in service

Proposed

A planned 200 MW batteries project, filed to come online in 2025.

Planned capacity200MW1 unit · not yet in service

Location

Multnomah County · PGE · WECC

Generating units

1 of 1 shown · none in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit SESD1200.0StorageBatteries2025Proposed

1 unit shown. Behind it, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →
UnitEventWhenMW
Unit SESD1new unit2025200 MW

Ownership & operations

Operating utility
Portland General Electric Co
Entity type
Investor-Owned Utility
Regulatory status
Regulated
Balancing authority
PGE
NERC region
WECC
EIA plant ID
67711

Common questions

How big is Seaside BESS?
200 MW across 1 unit, none of which is in service — all planned.
Who owns and operates it?
Operated by Portland General Electric Co, filed as investor-owned utility.
Which grid does it sell into?
PGE (Portland General Electric Company) is its balancing authority, inside NERC's WECC region.
What does it run on?
Batteries (200 MW).

Related pages

Oregon energyAll facilities in the state→Salem Smart Power CenterPower facility→ Salmonfly Solar and StoragePower facility→ Shell New Energies, Junction CityPower facility→ South Dunes Power PlantPower facility→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming