Fuel spend$208,4682023 · estimate
Capacity in service20.8MW1 unit · biomass
Net generation54.7GWh2023 · reported
Rank in South Carolina#60of 204 · by capacity · #4,391 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor30%2023
1 unit shown. Behind it, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; co-firing fuels and fuel-switching times; SO₂ scrubber type, sorbent and removal efficiency; NOₓ, particulate and mercury controls with compliance years; ownership stakes where a unit is jointly held.
See the engineering record →
How big is Savannah River Site Biomass Cogen?
20.8 MW across 1 generating unit in service.
Who owns and operates it?
Operated by Ameresco, filed as federally owned utility.
Which grid does it sell into?
SCEG (Dominion Energy South Carolina) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 2012.
When is it due to retire?
No retirement date has been filed for any operating unit at Savannah River Site Biomass Cogen. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned biomass.
How much does it spend on fuel?
An estimated $208,468 in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.