Operated by MidAmerican Energy Co, filed as investor-owned utility.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's MRO region.
How old is it?
The capacity-weighted average megawatt here came online in 1967. The oldest operating units are Unit 1, Unit 2, Unit 3 and Unit 4 (1966); the newest are Unit 7 and Unit 8 (1968).
When is it due to retire?
No retirement date has been filed for any operating unit at River Hills. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas.
How much does it spend on fuel?
An estimated $119,434 in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.