AMERICAN ENERGY ATLAS
Power·Minnesota

Rapids Energy Center

Grand Rapids, Itasca County, Minnesota · MISO · operated by ALLETE, Inc. · owned by Allete Inc

2023 · headline year
Fuel spend$6.44M2023 · estimate
Capacity in service28.4MW3 units · gas + hydro
CO₂ emitted67,557t2023 · reported to EPA · 3,094th highest of 6,030 in the US
Rank in Minnesota#82 (tied)of 767 · by capacity · #4,102 (tied) of 13,147 US
Reported suppliersNot reported2023

Location

Itasca County · MISO · MRO

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 1.3 TBtu · reported · $6.44M est.

CO₂ emitted, t · 2011–2023

050,000100,000150,000201120172023
Reported (through 2023)

Generating units

3 of 3 shown · 28.4 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 714.0Natural GasNatural Gas Steam Turbine1980Operating
Unit 612.5Natural GasNatural Gas Steam Turbine1969Operating
Unit HYD1.9WaterConventional Hydroelectric1943Operating

All 3 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; NOₓ, particulate and mercury controls with compliance years; stack height.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
Allete Inc · 100%
Operating utility
ALLETE, Inc.
Entity type
Investor-Owned Utility
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1002966
Balancing authority
MISO
NERC region
MRO
Gas pipeline
Great Lakes Gas Transmission LP
EIA plant ID
10686

Common questions

How big is Rapids Energy Center?
28.4 MW across 3 generating units in service — 26.5 MW of natural gas and 1.9 MW of hydro.
Who owns and operates it?
Owned by Allete Inc (100%) and operated by ALLETE, Inc., filed as investor-owned utility.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's MRO region.
How old is it?
The capacity-weighted average megawatt here came online in 1973. The oldest operating unit is Unit HYD (1943); the newest is Unit 7 (1980).
When is it due to retire?
No retirement date has been filed for any operating unit at Rapids Energy Center. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas.
How much does it spend on fuel?
An estimated $6.44M in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
How much CO₂ does it emit?
67,557 t in 2023, reported to the EPA — the 3,094th highest of 6,030 US facilities that reported. Down from 105,457 t in 2011.

Related pages

Minnesota energyAll facilities in the state→Community Wind North LLC30.0 MW operating capacity→ Community Wind South30.0 MW operating capacity→ Hutchinson Plant #128.4 MW operating capacity→ Ridgewind25.3 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming