Bernalillo County, New Mexico · PNM · operated by Quail Ranch Solar and Battery Energy Storage System
Capacity shown is planned or not in service
A planned 200 MW batteries project, filed to come online in 2026.
| Unit | Capacity MW | Fuel | Technology | Online | Status |
|---|---|---|---|---|---|
| Unit QRBES | 100.0 | Storage | Batteries | 2026 | Proposed |
| Unit QRPV | 100.0 | Solar | Solar Photovoltaic | 2026 | Proposed |
All 2 units shown. Behind each one, AEA holds the full engineering record: ownership stakes where a unit is jointly held.
See the engineering record →| Unit | Event | When | MW |
|---|---|---|---|
| Unit QRBES | new unit | 2026 | 100 MW |
| Unit QRPV | new unit | 2026 | 100 MW |