AMERICAN ENERGY ATLAS
Power·Pennsylvania

PWD Northeast WPCP Biogas Cogen Plant

Philadelphia County, Pennsylvania · PJM · operated by Philadelphia Water Department

2023 · headline year
Fuel spend$389,9402023 · estimate
Capacity in service5.6MW4 units · biomass
Net generation25GWh2023 · reported
Rank in Pennsylvania#183 (tied)of 256 · by capacity · #6,449 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor51%2023

Location

Philadelphia County · PJM · RFC

What it burns

2023 · reported

Share of reported fuel consumption

88% Landfill gas · 246,129 MMBtu · reported12% Natural gas · 34,508 MMBtu · reported · $389,940 est.

Landfill gas supplies 88% of the fuel energy it burned in 2023.

Reported fuel consumption, MMBtu · 2013–2023

0200,000400,000600,000201320182023
Reported (through 2023)

Generating units

4 of 4 shown · 5.6 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit NBG11.4BiogasOther Waste Biomass2013Operating
Unit NBG21.4BiogasOther Waste Biomass2013Operating
Unit NBG31.4BiogasOther Waste Biomass2013Operating
Unit NBG41.4BiogasOther Waste Biomass2013Operating

All 4 units shown. Behind each one, AEA holds the full engineering record: co-firing fuels and fuel-switching times; ownership stakes where a unit is jointly held.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Philadelphia Water Department
Entity type
Municipally Owned Utility
Regulatory status
Not Regulated
Balancing authority
PJM
NERC region
ReliabilityFirst (RFC)
EIA plant ID
58326

Common questions

How big is PWD Northeast WPCP Biogas Cogen Plant?
5.6 MW across 4 generating units in service.
Who owns and operates it?
Operated by Philadelphia Water Department, filed as municipally owned utility.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's ReliabilityFirst region.
How old is it?
The capacity-weighted average megawatt here came online in 2013. Every operating unit came online in 2013.
When is it due to retire?
No retirement date has been filed for any operating unit at PWD Northeast WPCP Biogas Cogen Plant. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned landfill gas and natural gas.
How much does it spend on fuel?
An estimated $389,940 in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.

Related pages

Pennsylvania energyAll facilities in the state→Bucknell University5.9 MW operating capacity→ ECP Uptown Campus5.6 MW operating capacity→ Blakely (PA) RTO BTM5.4 MW operating capacity→ Ephrata PA BTM5.4 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming