AMERICAN ENERGY ATLAS
Industrial + power·Maryland

Prince Georges County Brown Station Roa

Upper Marlboro, Prince George's County, Maryland · PJM · operated by Prince George's County · owned by Prince George's County Department of the Environmental Resource Recovery Div

Out of service2023 · headline year
Fuel spend$45,9402023 · estimate
Out-of-service capacity4.0MW4 units · none in service
CO₂ emitted41,826t2023 · reported to EPA · 4,034th highest of 6,030 in the US
Rank in Maryland#38of 46 · by reported CO₂ · #4,034 of 6,030 US
Reported suppliersNot reported2023

Location

Prince George's County · PJM · RFC

What its on-site power plant burns

2023 · reported

Share of reported fuel consumption

100% Landfill gas · 936 MMBtu · reported

CO₂ emitted, t · 2011–2023

0100,000200,000300,000201120172023
Reported (through 2023)

Generating units

4 of 4 shown · none in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 11.0Landfill gasLandfill Gas2003Out of service
Unit 21.0Landfill gasLandfill Gas2003Out of service
Unit 31.0Landfill gasLandfill Gas2003Out of service
Unit 41.0Landfill gasLandfill Gas2003Out of service

All 4 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Prince George's County
Entity type
Municipally Owned Utility
Regulatory status
Not Regulated
Industry sector
Waste
EPA facility ID
1002655
Balancing authority
PJM
NERC region
ReliabilityFirst (RFC)
EIA plant ID
55964

Common questions

How big is Prince Georges County Brown Station Roa?
4.0 MW across 4 units, none of which is in service — all on standby or out of service.
Who owns and operates it?
Owned by Prince George's County Department of the Environmental Resource Recovery Div (100%) and operated by Prince George's County, filed as municipally owned utility.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's ReliabilityFirst region.
What does it burn, and where does the fuel come from?
In 2023 its on-site power plant burned landfill gas.
How much does it spend on fuel?
An estimated $45,940 in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
How much CO₂ does it emit?
41,826 t in 2023, reported to the EPA — the 4,034th highest of 6,030 US facilities that reported. Down from 235,120 t in 2011.

Related pages

Maryland energyAll facilities in the state→Harford Waste Disposal Center44,442 t CO₂ in 2023→ US Navy Naval Support Facility Indian Head44,129 t CO₂ in 2023→ Naval Support Activity Bethesda38,782 t CO₂ in 2023→ Eastern Gas Transmission and Storage - Myersville Station (Tran)32,404 t CO₂ in 2023→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming