Power Generation Station (PGS) 2

Alameda County, California · CAISO · operated by East Bay Municipal Util Dist

2023 · headline year
Capacity in service4.6MW1 unit · biomass
Net generation20.4GWh2023 · reported
Rank in California#935 (tied)of 1,713 · by capacity · #7,766 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor51%2023

Location

Alameda County · CAISO · WECC

What it burns

2023 · reported

Share of reported fuel consumption

100% Landfill gas · 286,470 MMBtu · reported

Reported fuel consumption, MMBtu · 2011–2023

0200,000400,000600,000201120172023
Reported (through 2023)

Generating units

1 of 1 shown · 4.6 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 14.6BiogasOther Waste Biomass2011Operating

1 unit shown. Behind it, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
East Bay Municipal Util Dist
Entity type
Municipally Owned Utility
Regulatory status
Regulated
Balancing authority
CAISO
NERC region
WECC
EIA plant ID
57696

Common questions

How big is Power Generation Station (PGS) 2?
4.6 MW across 1 generating unit in service.
Who owns and operates it?
Operated by East Bay Municipal Util Dist, filed as municipally owned utility.
Which grid does it sell into?
CAISO (California Independent System Operator) is its balancing authority, inside NERC's WECC region.
How old is it?
The capacity-weighted average megawatt here came online in 2011.
When is it due to retire?
No retirement date has been filed for any operating unit at Power Generation Station (PGS) 2. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned landfill gas.

Related pages

California energyAll facilities in the state→Gas Utilization Facility4.6 MW operating capacity→ Nachtigall 1836-WD4.6 MW operating capacity→ SEPV Cuyama Hybrid4.6 MW operating capacity→ Terry 1818-WD4.6 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming