Wayne County, Georgia · SOCO · operated by BrightNight Power
Capacity shown is planned or not in service
A planned 2,500 MW solar photovoltaic project, filed to come online in 2027.
| Unit | Capacity MW | Fuel | Technology | Online | Status |
|---|---|---|---|---|---|
| Unit PEHA1 | 1,200.0 | Solar | Solar Photovoltaic | 2027 | Proposed |
| Unit PEHA | 900.0 | Solar | Solar Photovoltaic | 2028 | Proposed |
| Unit PEHA2 | 400.0 | Storage | Batteries | 2028 | Proposed |
All 3 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.
See the engineering record →| Unit | Event | When | MW |
|---|---|---|---|
| Unit PEHA1 | new unit | 2027 | 1,200 MW |
| Unit PEHA | new unit | 2028 | 900 MW |
| Unit PEHA2 | new unit | 2028 | 400 MW |