AMERICAN ENERGY ATLAS
Power·California

Parnassus Central Utility Plant

San Francisco County, California · CAISO · operated by University of California-San Francisco

2023 · headline year
Capacity in service13.4MW3 units · gas
Net generation68.5GWh2023 · reported
Rank in California#706 (tied)of 1,713 · by capacity · #5,057 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor58%2023

Location

San Francisco County · CAISO · WECC

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 944,318 MMBtu · reported

Reported fuel consumption, TBtu · 2012–2023

00.511.5201220182023
Reported (through 2023)

Generating units

3 of 3 shown · 13.4 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit GTG14.8Natural GasNatural Gas Fired Combined Cycle1996Operating
Unit GTG24.8Natural GasNatural Gas Fired Combined Cycle1996Operating
Unit STG13.8Natural GasNatural Gas Fired Combined Cycle1996Operating

All 3 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; co-firing fuels and fuel-switching times; NOₓ, particulate and mercury controls with compliance years.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
University of California-San Francisco
Entity type
Commercial
Regulatory status
Not Regulated
Balancing authority
CAISO
NERC region
WECC
EIA plant ID
58198

Common questions

How big is Parnassus Central Utility Plant?
13.4 MW across 3 generating units in service.
Who owns and operates it?
Operated by University of California-San Francisco, filed as commercial.
Which grid does it sell into?
CAISO (California Independent System Operator) is its balancing authority, inside NERC's WECC region.
How old is it?
The capacity-weighted average megawatt here came online in 1996. Every operating unit came online in 1996.
When is it due to retire?
No retirement date has been filed for any operating unit at Parnassus Central Utility Plant. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas.

Related pages

California energyAll facilities in the state→Java Solar, LLC13.5 MW operating capacity→ Nimbus13.4 MW operating capacity→ Roseburg Forest Products Biomass13.4 MW operating capacity→ Glass House Camarillo Cultivation13.2 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming