Orchard Park

Franklin County, Pennsylvania · PJM · operated by Borough of Chambersburg

2023 · headline year
Fuel spend$490,4382023 · estimate
Capacity in service24.0MW4 units · gas
Net generation16.2GWh2023 · reported
Rank in Pennsylvania#118 (tied)of 256 · by capacity · #4,248 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor8%2023

Location

Franklin County · PJM · RFC

What it burns

2023 · reported

Share of reported fuel consumption

99% Natural gas · 144,314 MMBtu · reported · $443,579 est.1% Oil & petroleum · 2,124 MMBtu · reported · $46,859 est.

Natural gas supplies 99% of the fuel energy it burned in 2023.

Reported fuel consumption, MMBtu · 2011–2023

0200,000400,000600,000201120172023
Reported (through 2023)

Generating units

4 of 4 shown · 24.0 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 106.0Natural GasNatural Gas Internal Combustion Engine2003Operating
Unit 116.0Natural GasNatural Gas Internal Combustion Engine2003Operating
Unit 86.0Natural GasNatural Gas Internal Combustion Engine2003Operating
Unit 96.0Natural GasNatural Gas Internal Combustion Engine2003Operating

All 4 units shown. Behind each one, AEA holds the full engineering record: co-firing fuels and fuel-switching times.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Borough of Chambersburg
Entity type
Municipally Owned Utility
Regulatory status
Regulated
Balancing authority
PJM
NERC region
ReliabilityFirst (RFC)
EIA plant ID
55997

Common questions

How big is Orchard Park?
24.0 MW across 4 generating units in service.
Who owns and operates it?
Operated by Borough of Chambersburg, filed as municipally owned utility.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's ReliabilityFirst region.
How old is it?
The capacity-weighted average megawatt here came online in 2003. Every operating unit came online in 2003.
When is it due to retire?
No retirement date has been filed for any operating unit at Orchard Park. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas and oil & petroleum.
How much does it spend on fuel?
An estimated $490,438 in 2023 — natural gas $443,579 and oil & petroleum $46,859. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.

Related pages

Pennsylvania energyAll facilities in the state→Harrisburg Facility24.1 MW operating capacity→ Blossburg24.0 MW operating capacity→ Wind Park Bear Creek24.0 MW operating capacity→ Wolf Run Energy LLC22.0 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming