AMERICAN ENERGY ATLAS
Power·Alaska

Orca

Valdez Cordova, Alaska · operated by Cordova Electric Coop, Inc

2023 · headline year
Capacity in service7.6MW3 units · oil · 1 more on standby or out of service
Net generation6.29GWh2023 · reported
Rank in Alaska#56of 142 · by capacity · #6,023 (tied) of 13,147 US
Reported suppliersNot reported2023

Location

Valdez Cordova

What it burns

2023 · reported

Share of reported fuel consumption

100% Oil & petroleum · 96,570 MMBtu · reported

Reported fuel consumption, MMBtu · 2011–2023

050,000100,000150,000201120172023
Reported (through 2023)

Generating units

8 of 8 shown · 7.6 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 73.6Distillate oilPetroleum Liquids2009Operating
Unit 32.5Distillate oilPetroleum Liquids1984Operating
Unit 6A1.5Distillate oilPetroleum Liquids2023Operating
Unit 51.1Distillate oilPetroleum Liquids2000Out of service
Unit 42.4Distillate oilPetroleum Liquids1984Retired 2024
Unit 61.1Distillate oilPetroleum Liquids2000Retired 2023
Unit 11.5Distillate oilPetroleum Liquidsnot reportedCanceled
Unit 21.5Distillate oilPetroleum Liquidsnot reportedCanceled

All 8 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Cordova Electric Coop, Inc
Entity type
Cooperative
Regulatory status
Regulated
EIA plant ID
789

Common questions

How big is Orca?
7.6 MW across 3 generating units in service. A further 5 units are listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Operated by Cordova Electric Coop, Inc, filed as cooperative.
How old is it?
The capacity-weighted average megawatt here came online in 2004. The oldest operating unit is Unit 3 (1984); the newest is Unit 6A (2023).
When is it due to retire?
No retirement date has been filed for any operating unit at Orca. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned oil & petroleum.

Related pages

Alaska energyAll facilities in the state→Haines7.8 MW operating capacity→ TNSG South Plant7.8 MW operating capacity→ Tok7.3 MW operating capacity→ Westward Seafoods6.6 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming