AMERICAN ENERGY ATLAS
Power·Alaska

NSB Wainwright Utility

North Slope, Alaska · operated by North Slope Borough Power & Light

2023 · headline year
Capacity in service3.0MW5 units · oil
Net generation6.84GWh2023 · reported
Rank in Alaska#82 (tied)of 142 · by capacity · #8,746 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor26%2023

Location

North Slope

What it burns

2023 · reported

Share of reported fuel consumption

100% Oil & petroleum · 76,731 MMBtu · reported

Reported fuel consumption, MMBtu · 2011–2023

030,00060,00090,000201120172023
Reported (through 2023)

Generating units

6 of 6 shown · 3.0 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit PG4A0.9Distillate oilPetroleum Liquids2001Operating
Unit PG50.9Distillate oilPetroleum Liquids2001Operating
Unit PG10.4Distillate oilPetroleum Liquids1988Operating
Unit PG20.4Distillate oilPetroleum Liquids1988Operating
Unit PG30.4Distillate oilPetroleum Liquids1989Operating
Unit PG40.3Distillate oilPetroleum Liquids1988Retired 2003

All 6 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
North Slope Borough Power & Light
Entity type
Municipally Owned Utility
Regulatory status
Regulated
EIA plant ID
7488

Common questions

How big is NSB Wainwright Utility?
3.0 MW across 5 generating units in service. A further 1 unit is listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Operated by North Slope Borough Power & Light, filed as municipally owned utility.
How old is it?
The capacity-weighted average megawatt here came online in 1996. The oldest operating units are Unit PG1 and Unit PG2 (1988); the newest are Unit PG4A and Unit PG5 (2001).
When is it due to retire?
No retirement date has been filed for any operating unit at NSB Wainwright Utility. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned oil & petroleum.

Related pages

Alaska energyAll facilities in the state→ESS Battery Microgrid3.0 MW operating capacity→ Kasidaya Creek Hydro3.0 MW operating capacity→ Craig (AK)2.8 MW operating capacity→ Gwitchyaa Zhee2.8 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming