AMERICAN ENERGY ATLAS
Power·Ohio

Northwest Ohio Wind

Paulding County, Ohio · PJM · operated by Northwest Ohio Wind, LLC

2023 · headline year
Fuel spend$02023 · no purchased fuel
Capacity in service110MW3 units · wind + solar + storage
Rank in Ohio#48of 189 · by capacity · #2,236 (tied) of 13,147 US

Location

Paulding County · PJM · RFC

Generating units

4 of 4 shown · 110 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit NWOH1105.0WindOnshore Wind Turbine2018Operating
Unit NWO-S4.0SolarSolar Photovoltaic2021Operating
Unit NWO-B0.8StorageBatteries2021Operating
Unit NWOH2100.0WindOnshore Wind Turbinenot reportedCanceled

All 4 units shown. Behind each one, AEA holds the full engineering record: turbine manufacturer, turbine count and hub height; panel technology, tracking and DC capacity; energy capacity in MWh, charge and discharge rates and use cases.

See the engineering record →

Ownership & operations

Operating utility
Northwest Ohio Wind, LLC
Entity type
Independent Power Producer
Regulatory status
Not Regulated
Balancing authority
PJM
NERC region
ReliabilityFirst (RFC)
EIA plant ID
59296

Common questions

How big is Northwest Ohio Wind?
110 MW across 3 generating units in service — 105 MW of wind, 4.0 MW of solar and 0.8 MW of storage. A further 1 unit is listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Operated by Northwest Ohio Wind, LLC, filed as independent power producer.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's ReliabilityFirst region.
How old is it?
The capacity-weighted average megawatt here came online in 2018. The oldest operating unit is Unit NWOH1 (2018); the newest are Unit NWO-S and Unit NWO-B (2021).
When is it due to retire?
No retirement date has been filed for any operating unit at Northwest Ohio Wind. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it run on?
Onshore Wind Turbine (105 MW), Solar Photovoltaic (4.0 MW) and Batteries (0.8 MW).
How much does it spend on fuel?
Nothing in 2023 — its units in service (batteries, onshore wind turbine and solar photovoltaic) burn no fuel, and it reports no fuel consumption to the EIA.

Related pages

Ohio energyAll facilities in the state→Dodson Creek Solar, LLC117 MW operating capacity→ Sycamore Creek Solar, LLC117 MW operating capacity→ Arche Energy Project, LLC107 MW operating capacity→ Paulding Wind Farm III101 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming