AMERICAN ENERGY ATLAS
Power·Wisconsin

Nortera Customer Hosted Solar

Fond du Lac County, Wisconsin · MISO · operated by Wisconsin Power & Light Co

Capacity shown is planned or not in service

Proposed

A planned 1.6 MW solar photovoltaic project, filed to come online in 2025.

Planned capacity1.6MW1 unit · not yet in service

Location

Fond du Lac County · MISO · MRO

Generating units

1 of 1 shown · none in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit PV11.6SolarSolar Photovoltaic2025Proposed

1 unit shown. Behind it, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →
UnitEventWhenMW
Unit PV1new unit20251.6 MW

Ownership & operations

Operating utility
Wisconsin Power & Light Co
Entity type
Investor-Owned Utility
Regulatory status
Regulated
Balancing authority
MISO
NERC region
MRO
EIA plant ID
67539

Common questions

How big is Nortera Customer Hosted Solar?
1.6 MW across 1 unit, none of which is in service — all planned.
Who owns and operates it?
Operated by Wisconsin Power & Light Co, filed as investor-owned utility.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's MRO region.
What does it run on?
Solar Photovoltaic (1.6 MW).

Related pages

Wisconsin energyAll facilities in the state→Nelson DeweyPower facility→ Niagara MillPower facility→ Northern Prairie 1Power facility→ Northern States FlambeauPower facility→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming