Retired — its last generating unit went out of service in 2018, ending 5.4 MW of capacity.
Retired capacity5.4MW3 units · none in service
Reported suppliersNot reported2023
Location
Reported fuel consumption, MMBtu · 2011–18
Reported (through 2018)
Generating units
3 of 3 shown · none in service
All 3 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.
See the engineering record →
Who supplies the fuel
2023
No fuel deliveries are reported for 2023.
Ownership & operations
- Operating utility
- American Mun Power-Ohio, Inc
- Entity type
- Municipally Owned Utility
- Regulatory status
- Regulated
- Balancing authority
- PJM
- NERC region
- ReliabilityFirst (RFC)
- EIA plant ID
- 7578
Common questions
How big is Napoleon?
5.4 MW across 3 units, none of which is in service — all retired.
Who owns and operates it?
Operated by American Mun Power-Ohio, Inc, filed as municipally owned utility.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's ReliabilityFirst region.
When is it due to retire?
It has already retired — the last unit retired in 2018.
What does it burn, and where does the fuel come from?
Its generating units are fuelled by distillate oil.